2023 Annual Stormwater Pipe Repair Project | 04-23-2024 | 04-01-2024 | Cynthia Moeller-Krass, P.E. | Construction | $2,173,774.27 | 96% | |
2023 Bridge Repair Program Project | 05-01-2024 | 01-31-2024 | Jason DeWald, P.E. | Construction | $416,000.00 | 10% | |
2023 Stormwater Structure Repair Project | 04-23-2024 | 07-28-2023 | Cynthia Moeller-Krass, P.E. | Construction | $103,138.00 | 99% | |
2024 Annual Stormwater Pipe Repair Project | 04-23-2024 | 10-25-2024 | Cynthia Moeller-Krass | Construction | $1,993,166.00 | 33% | |
2024 Mill and Overlay | 04-09-2024 | 12-01-2024 | Kenny Khongmaly | Construction | $6,702,937.35 | 99% | |
50th Street and Renee Drive CMP replacement | 05-06-2024 | 11-26-2024 | Arij Humeida, Project Manager | Pending City Council Approval | $2,192,840.00 | 22% | |
51st Ter and Millridge St CMP Rehabilitation Project | 04-30-2024 | 10-28-2024 | Riley McMullin, P.E. | Design | $1,510,200.00 | 24% | |
6000 Nieman Emergency RCB Replacement | 04-09-2024 | 12-29-2023 | Cynthia Moeller-Krass, P.E. | Construction | $790,000.00 | 85% | |
61st Ter & Rosehill Rd CMP Rehabilitation Project | 04-30-2024 | 10-28-2024 | Riley McMullin, P.E. | Design | $1,200,853.00 | 20% | |
65th Street and Lackman Road CMP Renewal Project | 04-30-2024 | 12-31-2024 | Jason DeWald | Design | $826,515.00 | 37% | |
75th Street and Switzer CMP Replacement | 05-06-2024 | 11-29-2024 | Arij Humeida, Project Manager | Design | $1,157,750.00 | 9% | |
80th Street Construction Project, Millridge Street to Woodland Road | 05-01-2024 | 12-31-2026 | Loren Snyder, P.E. | Construction | $0.00 | 0% | |
83rd and Monticello Road Traffic Signal (Lenexa and Shawnee Joint Project) | 04-30-2024 | 12-29-2023 | Loren Snyder, P.E. | Construction | $0.00 | 0% | |
Boyles Rezoning - 7460 Renner Rd | 05-07-2024 | 04-10-2024 | Mark Zielsdorf | Pending City Council Approval | $0.00 | 0% | |
Bristol Highland North Addition - 7800 block of Monticello Road | 05-07-2024 | 04-10-2024 | Mark Zielsdorf | Pending City Council Approval | $0.00 | 0% | |
Bristol Highlands East - First Plat | 10-24-2023 | 01-30-2023 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Bristol Highlands North, First and Second Plat | 07-12-2023 | 11-10-2022 | Mark Zielsdorf | Construction | $0.00 | 0% | |
Canyon Lakes, 1st, 2nd, 3rd, 4th, 5th and 6th Plats | 10-18-2023 | 04-20-2021 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Chick-Fil-A -11500 Shawnee Mission Parkway | 05-07-2024 | 11-09-2023 | Lauren Grashoff | Building Permit in Review | $0.00 | 0% | |
Concorp Building - 23810 W 83rd St | 09-05-2023 | 03-29-2023 | Lauren Grashoff | Construction | $0.00 | 0% | |
Contractors Park - 18760 Johnson Drive | 02-15-2024 | 09-07-2022 | Lauren Grashoff | Construction | $0.00 | 0% | |
Creekside Ridge - 6400 Silverheel Street | 11-14-2022 | 06-01-2021 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Cross Pointe, 3rd Plat - 5100-5300 Blocks of Noland Road | 11-09-2023 | 12-06-2022 | Mark Zielsdorf | Construction | $0.00 | 0% | |
Cross Pointe, 4th Plat - 5100-5300 Blocks of Noland Road | 08-08-2023 | 12-06-2022 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Crunch Fitness Parking Lot Expansion | 05-07-2024 | 05-07-2024 | Community Development Department | Construction | $0.00 | 0% | |
Estates of Timber Springs, 3rd, 4th, 5th 6th Plats | 08-08-2023 | 01-13-2021 | Mark Zielsdorf | Construction | $0.00 | 0% | |
Fire Station 71 and Fire Station 73 Facility Upgrades | 05-01-2024 | 10-15-2024 | Loren Snyder, P.E. | Construction | $26,213,308.00 | 84% | |
Gleason Road Stream Crossing | 04-30-2024 | 06-15-2024 | Ernie Longoria, P.E., PTOE | Construction | $878,557.25 | 39% | |
Hank's Garage - 5801 Nieman Rd | 02-22-2024 | 02-06-2024 | Lauren Grashoff | Approved | $0.00 | 0% | |
Hans Rudolph Building Addition | 02-21-2024 | 07-18-2023 | Lauren Grashoff | Construction | $0.00 | 0% | |
Harmony at Clear Creek - 64th and Silverheel | 03-26-2024 | 07-31-2023 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Heartland Logistics Park Building 3 - 24300 W 43rd Street | 12-20-2023 | 10-23-2023 | Lauren Grashoff | Construction | $0.00 | 0% | |
Hidden Creek Reserve Townhomes - 6700 Block of Hedge Lane Terrace | 10-10-2023 | 03-08-2022 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Hoffman Estates - 15101 Johnson Drive | 10-10-2023 | 08-22-2023 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Johnson Drive and Mauer Road CMP Renewal Project | 04-30-2024 | 12-31-2024 | Jason DeWald | Design | $1,053,072.00 | 53% | |
K-7 Logistics Centre - 79th Street & Monticello Terrace | 03-26-2024 | 06-01-2021 | Community Development Dept. | Approved | $0.00 | 0% | |
Kaw Valley Greenhouse / HyVee - 13550 W. 63rd St | 03-05-2024 | 02-06-2024 | Lauren Grashoff | Approved | $0.00 | 0% | |
KC Ice Center - 19900 Johnson Drive | 05-07-2024 | 12-19-2023 | Lauren Grashoff | Building Permit in Review | $0.00 | 0% | |
Kraft Tool Bldg Expansion - 8310 Hedge Lane Terrace | 02-15-2024 | 04-29-2022 | Lauren Grashoff | Building Permit in Review | $0.00 | 0% | |
Luxe Villas at the Greens - 23600 Block of Clear Creek Parkway | 03-07-2023 | 09-07-2022 | Mark Zielsdorf | Approved | $0.00 | 0% | |
Martin Family Dentistry - 6130 Nieman | 02-15-2024 | 08-01-2023 | Lauren Grashoff | Building Permit in Review | $0.00 | 0% | |
Maurer Road and Johnson Drive Intersection Improvements | 12-06-2023 | 08-07-2023 | Loren Snyder, P.E. | Future | $0.00 | 0% | |
McAnany Construction - 15320 Midland Drive | 01-18-2024 | 12-19-2023 | Lauren Grashoff | Approved | $0.00 | 0% | |
Med-Act - Midland & Bell | 08-22-2023 | 03-29-2023 | Lauren Grashoff | Construction | $0.00 | 0% | |
Mid-America West Sports Addition - 20200 Johnson Drive | 05-07-2024 | 04-10-2024 | Lauren Grashoff | Approved | $0.00 | 0% | |
Midland RCBs replacement (part of 2024 KDOT Midland Bridge Replacement, Project No. 435-46 KA-4275-02) | 04-30-2024 | 05-28-2025 | Ernie Longoria, P.E., PTOE | Design | $0.00 | 0% | |
Monrovia Street (55th Street to Johnson Drive) | 05-01-2024 | 12-31-2024 | Jason DeWald, P.E. | Construction | $2,985,000.00 | 97% | |
Monticello Road (Phase 1 & 2) | 04-30-2024 | 07-15-2023 | Ernie Longoria, P.E., PTOE | Construction | $19,850,000.00 | 99% | |
Nieman Road - Shawnee Mission Parkway to South City Limits | 05-01-2024 | 01-31-2024 | Jason DeWald, P.E. | Construction | $5,445,000.00 | 99% | |
Oak View Storage - 6425 Maurer Rd | 02-15-2024 | 11-10-2022 | Lauren Grashoff | Building Permit in Review | $0.00 | 0% | |