Fire Station 71 and Fire Station 73 Facility Upgrades
Name Fire Station 71 and Fire Station 73 Facility Upgrades
Date Updated 02-21-2024
Contact Loren Snyder, P.E.
Project Status Construction
Description Scope of work includes facility upgrades for Fire Station 71 (6501 Quivira Road) and Fire Station 73 (6805 Hedge Lane Terrace).
Status Details At the September 13, 2021 meeting, City Council approved the renovation option for Fire Station 71, renovation and building addition for Fire Station 73, and construction of several alternates.   

Design and construction phase services for GLMV Architecture were approved by City Council on October 11, 2021.

Schematic design activities were completed in January 2022.

Detail Design was completed in June 2022.

The next project phase was completion of Construction Documents in Q4 2022.

A public groundbreaking ceremony at Fire Station 71 - 6501 Quivira - was held December 21, 2022 at 4 PM.

Phase 1 of demolition at Fire Station 71 is complete.  Demolition at Fire Station 73 is complete.  Construction on the new Operations side of Fire Station 71is currently being completed. Construction of Fire Station 73 is also being completed.

Fire Station 71 has remained in operation during construction. 

https://www.cityofshawnee.org/departments/fire/about_us/fire_stations/fire_station_project

The Governing Body toured the Renovations of Fire Station No. 71 on November 20, 2023 at 5:00 PM

Due to the fact that a quorum of the Governing Body may be present, the City provided public notice pursuant to the Kansas Open Meetings Act.

This meeting took place at the Fire Station No. 71, 6501 Quivira Rd, Shawnee, KS.

Fire Station 73 will be substantially complete in March of 2024.  The second phase of phase two demolition is under way at Fire Station 71.









Contact Phone 913-742-6229
Contact Email lsnyder@cityofshawnee.org
This Is a City Project
Number 3520
This Is a Capital Improvement Project
Project Category Parks & Facilities
Design Firm GLMV Architecture
Construction Contract Turner Construction
Inspection Firm GLMV Architecture
Start Date 10-01-2022
Estimated End Date 10-15-2024
Budget Information
As of Mar 6 2024
Current Budget $26,213,308.00
Current Commitments $25,151,727.40
Paid-to-Date $19,877,487.00
Percentage Paid 79%
Project Files
File Name
Download
City Council_Memorandum and Attachments_09132021.pdf
City Council_Memorandum and Attachments_10112021.pdf