7410 Switzer/Larsen 65th to 67th
Name: 7410 Switzer/Larsen 65th to 67th
Date Updated: 08-10-2026
Contact: Jim Johnson, Project Manager
Project Status: Design
Description: Site 1: 75th & Switzer – Replacement of approximately 1007 LF of failing storm sewer system (CMP and 8 structures).

Site 2: Larsen – 65th to 67th – Replacement of approximately up to 1115 LF of failing storm sewer system (CMP and 3 structures).
Status Details: Construction Bid Award to City Council for Approval August 10, 2026
Contact Phone: 913-742-6229
Contact Email: jrjohnson@cityofshawnee.org
This Is a City Project:
Number: 3631
This Is a Capital Improvement Project:
Project Category: Drainage Improvements
Design Firm: Professional Engineering Consultants
Construction Contract: TBD
Inspection Firm: TBD
Start Date: 07-07-2026
Estimated End Date: 12-31-2026
Budget Information
As of Sep 2 2026
Current Budget $2,410,328.00
Current Commitments $312,650.00
Paid-to-Date $290,264.00
Percentage Paid 92%
Project Files
File Name
Download
No files to show...
Project Images
File Name
View
Download
No images to show...