2026 SIP: 51st Street, between Black Swan Drive and Quivira Road
Name:
2026 SIP: 51st Street, between Black Swan Drive and Quivira Road
Date Updated:
02-04-2026
Contact:
Jason Dewald
Project Status:
Design
Description:
The section of 51st Street from Black Swan Drive to Quivira Road is a two-lane road with open ditches and does not include pedestrian or bike facilities.
One of the goals of this project is to replace the open ditches with improved stormwater infrastructure and add walking and biking facilities that support a safer, more walkable, and better connected neighborhood.
Status Details:
Project is currently in the design phase. Utility relocations are anticipated to begin late spring of 2026. Project construction is anticipated to begin in the fall of 2026
Contact Phone:
913-742-6234
Contact Email:
jdewald@cityofshawnee.org
This Is a City Project:
Number:
3622
This Is a Capital Improvement Project:
Project Category:
Street Improvements
Design Firm:
BG Consultants, Inc.
Construction Contract:
TBD
Inspection Firm:
TBD
Start Date:
06-10-2025
Estimated End Date:
12-15-2026
Budget Information
As of Feb 4 2026
Current Budget
$3,039,900.00
Current Commitments
$418,653.00
Paid-to-Date
$295,407.00
Percentage Paid
70%