Name: |
2026 Annual Stormwater Pipe Repair |
Date Updated: |
10-01-2025 |
Contact: |
Cynthia Moeller-Krass, P.E. |
Project Status: |
Design |
Description: |
This stormwater project will rehabilitate failing stormwater infrastructure by either full replacement or lining. This project is anticipated to include repairs at 30-40 locations city-wide. These stormwater pipes selected for repair are typically prioritized by known sinkholes or pipes under roads scheduled for pavement mill and overlay work in the next two years. |
Status Details: |
The design engineer submitted 40 locations for review and inclusion on the upcoming project. Staff is reviewing plans and proritizing work scope based on urgency, need and budget. The next steps will include contacting adjacent property owners of the work and acquiring access agreements to complete the work. A preliminary utiltiy meeting is anticipated in mid-October. |
Contact Phone: |
913-742-6236 |
Contact Email: |
cmoeller-krass@cityofshawnee.org |
This Is a City Project: |
|
Number: |
3636 |
This Is a Capital Improvement Project: |
|
Project Category: |
Drainage Improvements |
Design Firm: |
Olsson |
Construction Contract: |
TBD |
Inspection Firm: |
City Staff and Olsson |
Start Date: |
12-15-2025 |
Estimated End Date: |
10-01-2026 |