2026 Annual Stormwater Pipe Repair
Name: 2026 Annual Stormwater Pipe Repair
Date Updated: 01-21-2026
Contact: Cynthia Moeller-Krass, P.E.
Project Status: Construction
Description: This stormwater project will rehabilitate failing stormwater infrastructure by either full replacement or lining.  This project was awarded to Wiedenmann, Inc. and includes  repairs at 18 locations city-wide. These stormwater pipes selected for repair are typically prioritized by known sinkholes or pipes under roads scheduled for pavement mill and overlay work in the next two years. 
Status Details: The construction project was awarded to Wiedenmann Inc in early December, the preconstruction meeting with utilities and the contractor was held on Jan 13, 2026. Construction is expected to start in early March.  Awarded repair locations were selected based on proritizing work scope based on urgency, need and budget. Property owners adjacent to the work locations are being contacted for access agreements to complete the work. 

Wiedenmann is expected to start work on this project in early March. Property owners will receive door hangers immediately before the start of work near their home.  
Contact Phone: 913-742-6236
Contact Email: cmoeller-krass@cityofshawnee.org
This Is a City Project:
Number: 3636
This Is a Capital Improvement Project:
Project Category: Drainage Improvements
Design Firm: Olsson
Construction Contract: Wiedenmann, Inc. 
Inspection Firm: City Staff and Olsson
Start Date: 03-02-2026
Estimated End Date: 10-30-2026
Budget Information
As of Feb 4 2026
Current Budget $0.00
Current Commitments $0.00
Paid-to-Date $0.00
Percentage Paid 0%