Status Details: |
The contractor has Final Repair maps for the 2025 project are attached. started work and will proceed as structures and pipe materials become available.
The intention is to complete pipe repair locations in advance of the 2025 Mill & Overlay project. The intent is to generally complete map locations on Mill & Overlay Streets first. These streets can be seen on the " 2025 Shawnee PR Map Update" attachment as gold lines.
Wiedenmann is currently working on Maps 8, 28, 29, and 34, as well as the 4900 Roundtree Streambank Stabilization portion of the project. Wiedenmann is starting a 3rd crew on July 14th.
"Starting Soon" Map locations for June and July include: Maps 11, 13, and 42-45.
Maps planned for late July, August and September include: Maps 7, 15, 25, 26 ,30, 32, 35, 40, 41, and any late addition locations.
Completed Maps: Map 1, 22, 36, and 39. Maps Substantially Completed: Maps 3, 4, 5, 6, 17, 19, and 21.
07/01/25 Repair Updates:
Completed - Maps 1, 21, 22, 36 and 39 Substantially Completed - Maps 3, 4, 5, 6, 12, 14, 17, 19 and 37 In Progress - Maps 18, 28, 29, 34 and 49th & Rountree
09/08/25 Repair Updates:
Completed - Maps 1, 21, 22, 36, 39 & 28 Substantially Completed - Maps 3, 4, 5, 6, 8, 12, 14, 17, 18, 19, 34, 37, 43, 44 & 45 In Progress - Maps 7, 29 & 46 |