Name: |
2025 Annual Stormwater Pipe Repair |
Date Updated: |
05-28-2025 |
Contact: |
Cynthia Moeller-Krass |
Project Status: |
Construction |
Description: |
The stormwater project will remove and replace or line up to 4460 linear feet of failing pipes at 30 locations throughout the City - see attached maps for locations. In addition, a streamcut on the south side of Garrett Park on a tributary to Mill Creek is to be restored with rock and check dams near 49th and Roundtree Pedestrian Bridge and two adjacent downstream storm pipe outfalls. |
Status Details: |
The contractor has started work and will proceed as structures and pipe materials become available.
Wiedenmann is currently working on Maps 18, 28, 29, 34, and 37. Wiedenmann started with additional crews on April 14th.
"Starting Soon" Map locations for June and July include: Maps 11, 12, 13, 14, and 4900 Roundtree.
Maps planned for late July, August and September include: Maps 7 ,8, 15, 25, 26 ,30, 32, 35, 40, 41, and 42.
Maps Substantially Completed: Maps 3, 4, 5, 6, 17, 19, and 21.
Completed Maps: Map 1, 22, 36, and 39.
The intention is to complete pipe repair locations in advance of the 2025 Mill & Overlay project. The intent is to generally complete map locations on Mill & Overlay Streets first. These streets can be seen on the " 2025 Shawnee PR Map Update" attachment as gold lines.
Final Repair maps for the 2025 project are attached. |
Contact Phone: |
913-742-6236 |
Contact Email: |
cmoeller-krass@cityofshawnee.org |
This Is a City Project: |
|
Number: |
3605 |
This Is a Capital Improvement Project: |
|
Project Category: |
Drainage Improvements |
Design Firm: |
Olsson |
Construction Contract: |
Wiedenmann, Inc. |
Inspection Firm: |
Olsson |
Start Date: |
08-05-2024 |
Estimated End Date: |
10-31-2025 |