| Name: |
2025 Annual Stormwater Pipe Repair |
| Date Updated: |
03-28-2026 |
| Contact: |
Cynthia Moeller-Krass, P.E. |
| Project Status: |
Construction |
| Description: |
The stormwater project will remove and replace or line up to 4460 linear feet of failing pipes at 30 locations throughout the City - see attached maps for locations. In addition, a streamcut on the south side of Garrett Park on a tributary to Mill Creek is to be restored with rock and check dams near 49th and Roundtree Pedestrian Bridge and two adjacent downstream storm pipe outfalls. |
| Status Details: |
The contractor has Final Repair maps for the 2025 project are attached.
The intention is to complete pipe repair locations in advance of the 2025 Mill & Overlay project. The intent is to generally complete map locations on Mill & Overlay Streets first. These streets can be seen on the " 2025 Shawnee PR Map Update" attachment as gold lines. The contractor will then complete all other locations and any emergency locations that are added later by change order.
Wiedenmann has only 2 maps - Maps 13 and Map 15 that have not yet been started. These 2 locations are scheduled to start on April 6th and be completed by May 1st. As of March 23rd all locations have been fully completed except for 9 that still need sod installed. This sod installation is expected to occur soon. |
| Contact Phone: |
913-742-6236 |
| Contact Email: |
cmoeller-krass@cityofshawnee.org |
| This Is a City Project: |
|
| Number: |
3605 |
| This Is a Capital Improvement Project: |
|
| Project Category: |
Drainage Improvements |
| Design Firm: |
Olsson |
| Construction Contract: |
Wiedenmann, Inc. |
| Inspection Firm: |
Olsson |
| Start Date: |
08-05-2024 |
| Estimated End Date: |
03-27-2026 |