2025 Mill and Overlay Project
Name: 2025 Mill and Overlay Project
Date Updated: 05-07-2025
Contact: Kenny Khongmaly
Project Status: Construction
Description: This project includes curb and gutter replacement, sidewalk replacement, full depth asphalt patching, pavement markings and asphalt overlay.
Status Details: This project was awarded to McAnany Construction.  The notice to proceed is set for April 21, 2025.
Contact Phone: 913-742-6267
Contact Email: kkhongmaly@cityofshawnee.org
This Is a City Project:
Number: 3616
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: In House
Construction Contract: McAnany Construction Inc.
Inspection Firm: In House
Start Date: 04-15-2026
Estimated End Date: 09-12-2025
Budget Information
As of Jun 4 2025
Current Budget $2,807,000.00
Current Commitments $2,626,262.26
Paid-to-Date $323,976.00
Percentage Paid 12%