2025 Mill and Overlay Project
Name: 2025 Mill and Overlay Project
Date Updated: 11-05-2025
Contact: Kenny Khongmaly
Project Status: Construction
Description: This project includes curb and gutter replacement, sidewalk replacement, full depth asphalt patching, pavement markings and asphalt overlay.
Status Details: This project was awarded to McAnany Construction.  The notice to proceed is set for April 21, 2025.  The contractor is working on the last few streets and looking to be completed with the mill and overlay portion by the end of November.
Contact Phone: 913-742-6267
Contact Email: kkhongmaly@cityofshawnee.org
This Is a City Project:
Number: 3616
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: In House
Construction Contract: McAnany Construction Inc.
Inspection Firm: In House
Start Date: 04-15-2026
Estimated End Date: 09-12-2025
Budget Information
As of Dec 3 2025
Current Budget $2,807,000.00
Current Commitments $2,800,000.00
Paid-to-Date $2,007,127.00
Percentage Paid 71%