2025 Bridge Repair Program
Name: 2025 Bridge Repair Program
Date Updated: 10-02-2025
Contact: Riley McMullin, P.E.
Project Status: Pending City Council Approval
Description: The Project provides for construction of rehabilitation work on eight bridges throughout Shawnee, KS. Work includes, but is not limited to, repair of concrete deck, drip line, curb, rail, wall, ceiling, approach slabs, clearing and grubbing, mud jacking, sealing, seeding, and traffic control.
Status Details: Bidding has ended and the construction contract is pending City Council Approval.
Contact Phone: 913-742-6224
Contact Email: rmcmullin@cityofshawnee.org
This Is a City Project:
Number: 3618
This Is a Capital Improvement Project:
Project Category: Bridge Improvements
Design Firm: Lochner
Construction Contract: TBD
Inspection Firm: TBD
Start Date: 03-02-2026
Estimated End Date: 05-29-2026
Budget Information
As of Oct 1 2025
Current Budget $216,000.00
Current Commitments $47,317.00
Paid-to-Date $40,293.00
Percentage Paid 85%