Name: |
Blackfish Pkwy - West of Pflumm |
Date Updated: |
09-03-2025 |
Contact: |
Jim Johnson, Project Manager |
Project Status: |
Future |
Description: |
Replacement of approximately 2555-LF of failing storm sewer system & lining of 58 LF of 36” (CMP, Lining, 15 structures and 4 structure repairs) • Location 1: Blackfish Parkway & Lackman Road • Location 2: Midland to Acuff • Location 3: Blackfish and Pflumm
|
Status Details: |
RFQ scoring process for Design Consultant |
Contact Phone: |
913-742-6229 |
Contact Email: |
jrjohnson@cityofshawnee.org |
This Is a City Project: |
|
Number: |
3632 |
This Is a Capital Improvement Project: |
|
Project Category: |
Drainage Improvements |
Design Firm: |
TBD |
Construction Contract: |
TBD |
Inspection Firm: |
TBD |
Start Date: |
05-04-2026 |
Estimated End Date: |
09-04-2026 |