| Name: |
Goddard Street and Shawnee Mission Parkway & 61st Street and Melrose Lane CMP Replacement |
| Date Updated: |
01-09-2026 |
| Contact: |
Jim Johnson, Project Manager |
| Project Status: |
Construction |
| Description: |
This project includes the replacement of Corrugated Metal Pipe (CMP) in the following locations.
Site 1: This site is located along Goddard Street from Shawnee Mission Parkway north to West 62nd Street.
Site 2: This site is located at West 61st Street and Melrose Lane.
Combined this project will replace approximately 1,000 linear feet of aging and deteriorating stormwater infrastructure. |
| Status Details: |
The Government Body approved the Engineering Services for this project during the October 14, 2024 City Council Meeting.
The project is currently under final design and the anticipated schedule is as follows:
- Construction is anticipated to begin in the summer of 2025 - This project is planned to be constructed by March 2026 |
| Contact Phone: |
913-742-6229 |
| Contact Email: |
jjohnson@cityofshawnee.org |
| This Is a City Project: |
|
| Number: |
3601 |
| This Is a Capital Improvement Project: |
|
| Project Category: |
Drainage Improvements |
| Design Firm: |
Olsson |
| Construction Contract: |
TBD |
| Inspection Firm: |
TBD |
| Start Date: |
10-21-2024 |
| Estimated End Date: |
12-23-2025 |