Name |
2023 Annual Stormwater Pipe Repair Project |
Date Updated |
06-06-2023 |
Contact |
Cynthia Moeller-Krass, P.E. |
Project Status |
Construction |
Description |
This stormwater project will remove and replace or cure-in-place line 46 failing pipes at 23 locations throughout the City - see attached Maps for locations. Funding for this infrastructure repair project is through the Stormwater Utility Fund. The fund is comprised of fees that are paid by every property owner in Shawnee.
In general, this annual project focuses on repairing pipes beneath roads scheduled for the annual pavement mill and overlay project or failed pipes that have resulted in sinkholes in resident's yards. |
Status Details |
Final Repair Maps for the 2023 project are completed and attached. Project notices and Access Agreements were sent to affected residents in early and mid-October. Final Plan Approval to bid the project for construction is on the October 24, 2022 City Council Agenda. Project award for Construction is scheduled for December 12, 2022.
The 2023 Pipe Repair Project was awarded to Wiedenmann Inc. on December 12, 2022, in the amount of $1,618,711.67.
The Notice to Proceed was issued on January 23, 2023 The anticipated Contract Completion date is September 10, 2023.
Phase 1 (January - March 15th): MAPS 1, 2, 3 4 & 26 Phase 2 (January - April 15th): MAPS 14, 15, 16, 27 & 17/Alt 5 Phase 3 (January - May 15th): MAPS 5, 6, 7, 9, 11, 12, 13, Alt 2 & 8/Alt 4
Phase 4 (January - June 15th): MAPS 18 & 22/Alt 3
03/08/23 UPDATE: The below noted Maps are under construction and approximately 15% of the work is in various construction phases. In Progress - Maps 7 & 14 Substantially Complete - Maps 1, 3, & 5
04/21/23 UPDATE: The below noted Maps are under construction and approximately 40% of the work is in various construction phases. In Progress - Maps 8, 15, 17 and 26 Substantially Complete - Maps 13, 14, 16, 22, Alt 2 and Alt 7 Complete - Maps 1, 3, 4, 5, 7, 9 and 12
05/26/23 UPDATE: The below noted Maps are under construction and approximately 55% of the work is in various construction phases.
In Progress - Maps 8 and 15 Substantially Complete - Maps 13, 14, 16, 17, 22, 26, 28, Alt 2 and Alt 7 Complete - Maps 1, 3, 4, 5, 7, 9, 11 and 12 |
Contact Phone |
913-742-6236 |
Contact Email |
cmoeller-krass@cityofshawnee.org |
This Is a City Project |
|
Number |
3554 |
This Is a Capital Improvement Project |
|
Project Category |
Drainage Improvements |
Design Firm |
Olsson |
Construction Contract |
Wiedemann Inc |
Inspection Firm |
City/ Olsson |
Start Date |
08-01-2022 |
Estimated End Date |
10-01-2023 |