Status Details |
Final Repair Maps for the 2023 project are completed and attached. Project notices and Access Agreements were sent to affected residents in early and mid-October. Final Plan Approval to bid the project for construction is on the October 24, 2022 City Council Agenda. Project award for Construction is scheduled for December 12, 2022.
The 2023 Pipe Repair Project was awarded to Wiedenmann Inc. on December 12, 2022, in the amount of $1,618,711.67.
The Notice to Proceed was issued on January 23, 2023 The anticipated Contract Completion date is September 10, 2023.
Phase 1 (January - March 15th): MAPS 1, 2, 3 4 & 26 Phase 2 (January - April 15th): MAPS 14, 15, 16, 27 & 17/Alt 5 Phase 3 (January - May 15th): MAPS 5, 6, 7, 9, 11, 12, 13, Alt 2 & 8/Alt 4
Phase 4 (January - June 15th): MAPS 18 & 22/Alt 3
03/08/23 UPDATE: The below noted Maps are under construction and approximately 15% of the work is in various construction phases. In Progress - Maps 7 & 14 Substantially Complete - Maps 1, 3, & 5
04/21/23 UPDATE: The below noted Maps are under construction and approximately 40% of the work is in various construction phases. In Progress - Maps 8, 15, 17 and 26 Substantially Complete - Maps 13, 14, 16, 22, Alt 2 and Alt 7 Complete - Maps 1, 3, 4, 5, 7, 9 and 12
05/26/23 UPDATE: The below noted Maps are under construction and approximately 55% of the work is in various construction phases.
In Progress - Maps 8 and 15 Substantially Complete - Maps 13, 14, 16, 17, 22, 26, 28, Alt 2 and Alt 7 Complete - Maps 1, 3, 4, 5, 7, 9, 11 and 12
07/13/23 UPDATE: The below noted Maps are under construction and approximately 70% of the work is in various construction phases.
In Progress - Maps 6, 8 18 and 27 Substantially Complete - Maps 13, 14, 15, 16, 17, 22, 28, Alt 2 and Alt 7 Complete - Maps 1, 3, 4, 5, 7, 9, 11 and 12
08/28/23 UPDATE: The below noted Maps are under construction and approximately 90% of the work is in various construction phases.
In Progress - Map 2, 27, and new locations 29 and 30. Substantially Complete - Maps 6, 8B, 8C, 13, 14, 15, 16, 17, 18A, 18B, 22, 26, 28, Alt 2 & Alt 7 Complete - Maps 1, 3, 4, 5, 7, 8A, 8D, 9, 11 and 12
Sod will begin being installed in all completed locations in mid-September.
|