2023 Stormwater Structure Repair Project
Name 2023 Stormwater Structure Repair Project
Date Updated 04-23-2024
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description The Project provides for the removal and replacement or repair of twelve (12) storm structures (inlets, junction boxes, etc.) and associated site restoration. Construction will also include surface restoration including concrete curb and gutter, concrete sidewalk, concrete inlet tops, street repair, sod, and other items. These structure repair or replacement locations are at 12 locations throughout the City. See attached overall map for locations and the Workscope Chart for the planned repair at each location.

This project is to rehabilitate structures on roads that are scheduled on the 2023 Mill & Overlay project. 
Status Details Final Plans for the Structure Repair project are completed and the overall location map and structure repair workscope are attached. All work is located in right-of-ways so no property owner access agreements are necessary. Final Plan approval to bid this construction work is scheduled to be on the January 9, 2023 City Council Agenda.

5/25/23  This project is approximately 38% complete. 

The below items are completed.
    S-3456 at Johnson Drive & Rosehill
    S-4146 at Midland & Maurer
Structure below structure tops are completed.
    S-3232 at 62nd Ter & Richards
    S-419  at 62nd Ter & Richards


7/13/23  This project is approximately 65% complete. 

The below items are completed.
    S-419 at Shawnee Mission Parkway & Long
    S-3232 at Shawnee Mission Parkway & Long
    S-7701 at 47th & Aminda
    S-9420 at 47th & Aminda
    S-7485 at 47th & Aminda
The below structures are in progress:
    S-3232 at 62nd Ter & Richards
    S-11933 at 62nd Ter & Richards
    S-4146 at Midland & Maurer
    S-3459 at Johnson & Rosehill
    S-2881 at 77th & Nieman
    S-2882 at 77th & Nieman


8/28/23  This project is approximately 85% complete. 

The below items are completed.
    S-419 at Shawnee Mission Parkway & Long
    S-3232 at Shawnee Mission Parkway & Long
    S-7701 at 47th & Aminda
    S-9420 at 47th & Aminda
    S-7485 at 47th & Aminda
The below structures are in progress:
    S-11933 at 62nd Ter & Richards
    S-4146 at Midland & Maurer
    S-3465 at 13320 W 62nd Ter
    S-3466 at 13320 W 62nd Ter
    S-3459 at Johnson & Rosehill
    S-2881 at 77th & Nieman
    S-2882 at 77th & Nieman

Sod should be installed at all locations in mid-September.

3/6/2024 UPDATE - Sod and Replacement Inlet lids to be completed by 3/15/2024.

This project is completed and the final change order was approved by City Council on Monday, April 22, 2024.
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3569
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson
Construction Contract TBD
Inspection Firm City of Shawnee
Start Date 12-30-2022
Estimated End Date 07-28-2023
Budget Information
As of Mar 6 2024
Current Budget $103,138.00
Current Commitments $103,138.00
Paid-to-Date $100,780.00
Percentage Paid 97%
Project Files
File Name
Download
2023_Structure_Repair - Location-Map.pdf
2023_Structure_Repair - Workscope-Summary-Table.pdf
Project Images
File Name
View
Download
No images to show...