75th Street and Switzer CMP Replacement
Name: 75th Street and Switzer CMP Replacement
Date Updated: 10-02-2024
Contact: Arij Humeida, Project Manager 
Project Status: Construction
Description: The Project will replace 10 pipes and 11 structures. 6 pipes (~560 feet)and 7 structures are fully in Shawnee and 2 pipes cross the city limit line with Overland Park. 2 pipes and 3 structures are fully in OP. All pipes and structures are considered eligible for County SMP cost sharing. The stormwater conveyance system is in a tight corridor between commercial properties.
Status Details: ABAY Construction was the lowest bid. It will going to city council July 8, 2024 to recommend awarding the project to ABAY Construction start construction in August.
Contact Phone: 913-742-6223
Contact Email: ahumeida@cityofshawnee.org
This Is a City Project:
Number: 3577
This Is a Capital Improvement Project:
Project Category: Drainage Improvements
Design Firm: Olsson
Construction Contract: ABAY Construction 
Inspection Firm: Olsson
Start Date: 07-22-2024
Estimated End Date: 11-29-2024
Budget Information
As of Nov 6 2024
Current Budget $1,157,750.00
Current Commitments $179,355.00
Paid-to-Date $51,981.00
Percentage Paid 28%
Project Files
File Name
Download
75th&Switzer_Final_Plans.pdf