75th Street and Switzer CMP Replacement
Name: 75th Street and Switzer CMP Replacement
Date Updated: 02-07-2025
Contact: Arij Humeida, Project Manager
Project Status: Construction
Description: The Project will replace 10 pipes and 11 structures. 6 pipes (~560 feet)and 7 structures are fully in Shawnee and 2 pipes cross the city limit line with Overland Park. 2 pipes and 3 structures are fully in OP. All pipes and structures are considered eligible for County SMP cost sharing. The stormwater conveyance system is in a tight corridor between commercial properties.
Status Details: ABAY Construction was the lowest bid. It will going to city council July 8, 2024 to recommend awarding the project to ABAY Construction start construction in August.
Contact Phone: 913-742-6223
Contact Email: ahumeida@cityofshawnee.org
This Is a City Project:
Number: 3577
This Is a Capital Improvement Project:
Project Category: Drainage Improvements
Design Firm: Olsson
Construction Contract: ABAY Construction 
Inspection Firm: Olsson
Start Date: 07-22-2024
Estimated End Date: 01-30-2025
Budget Information
As of Mar 5 2025
Current Budget $1,157,750.00
Current Commitments $722,844.94
Paid-to-Date $588,238.00
Percentage Paid 81%
Project Files
File Name
Download
75th&Switzer_Final_Plans.pdf