2024 Annual Stormwater Pipe Repair Project
Name 2024 Annual Stormwater Pipe Repair Project
Date Updated 04-23-2024
Contact Cynthia Moeller-Krass
Project Status Construction
Description This stormwater project will remove and replace or cure-in-place line 62 failing pipes at 30 locations throughout the City - see attached Maps for locations. Funding for this infrastructure repair  project is through the Stormwater Utility Fund. The fund is comprised of fees that are paid by every property owner in Shawnee.
Status Details Final Repair Maps for the 2024 project are completed and attached. Project notices and Access Agreements were sent to affected residents in October.   Final Plan Approval to bid the project for construction is on the November 13, 2023 City Council Agenda. Project award for Construction is scheduled for December 11, 2023. 

3/8/2024 UPDATE - The contractor is working on this project and different areas are in various stages of construction.

   SUBSTANTIALLY COMPLETED - Map 16, 17, 25, & 40

   IN PROGRESS - MAP 1, 36 & 38
  

04/9/2024 UPDATE - The contractor is working on this project and different areas are in various stages of construction. Approximately 25% of the project is completed.

   COMPLETED - Map 1, 16, 17 & 38

   SUBSTANTIALLY COMPLETED - Map 12, 24, 25, 26, 33, 36, 40 & Alt 1

   IN PROGRESS - MAP 11, 23, 30 & 32
   
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3587
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson
Construction Contract TBD
Inspection Firm TBD
Start Date 07-04-2023
Estimated End Date 10-25-2024
Budget Information
As of Mar 6 2024
Current Budget $1,993,166.00
Current Commitments $1,993,166.00
Paid-to-Date $0.00
Percentage Paid 0%
Project Files
File Name
Download
2024_Pipe_Repair_Maps_website_1_11072023.pdf
Project Images
File Name
View
Download
No images to show...