| Name: |
Lakecrest Drive and W 55TH & Brownridge CMP Replacement. |
| Date Updated: |
11-04-2025 |
| Contact: |
Jim Johnson, Project Manager |
| Project Status: |
Approved |
| Description: |
This project includes the replacement of Corrugated Metal Pipe (CMP) in the following locations.
Site 1: Lakecrest Drive and 55th– Replacement of approximately 637-LF of failing storm sewer system (CMP and 1 structures). Site 2: Brownridge – Replacement of approximately 211-LF of failing storm sewer |
| Status Details: |
Closeout Phase and Final Cleanup |
| Contact Phone: |
913-742-6229 |
| Contact Email: |
jrjohnson@cityofshawnee.org |
| This Is a City Project: |
|
| Number: |
3600 |
| This Is a Capital Improvement Project: |
|
| Project Category: |
Drainage Improvements |
| Design Firm: |
RIC |
| Construction Contract: |
Infrastructure Solutions LLC |
| Inspection Firm: |
RIC |
| Start Date: |
09-08-2025 |
| Estimated End Date: |
11-07-2025 |