Midland RCBs replacement (part of 2024 KDOT Midland Bridge Replacement, Project No. 435-46 KA-4275-02)
Name: Midland RCBs replacement (part of 2024 KDOT Midland Bridge Replacement, Project No. 435-46 KA-4275-02)
Date Updated: 09-04-2024
Contact: Jason DeWald, P.E.
Project Status: Design
Description: The Kansas Department of Transportation (KDOT) will be completely reconstructing the I-435 bridge decks over Midland Drive in 2024. Roadway and lane closures of Midland Drive are expected during construction. Staff has identified the twin 150 foot long, 4'x8' reinforced concrete boxes (RCBs) on Midland Drive between the I-435 northbound ramps and Renner Road as a priority for replacement and completing this work as part of the KDOT Project will reduce overall travel delays and potentially result in construction cost savings.
Status Details: Currently under construction. Estimated 18 month timeframe
KDOT continues to administer the project through construction.
Contact Phone: 913-742-6312
Contact Email: jdewald@cityofshawnee.org
This Is a City Project:
Number: 3574
This Is a Capital Improvement Project:
Project Category: Drainage Improvements
Design Firm: Olsson
Construction Contract: TBD
Inspection Firm: TBD
Start Date: 11-28-2022
Estimated End Date: 05-28-2025
Budget Information
As of Dec 4 2024
Current Budget $1,185,600.00
Current Commitments $0.00
Paid-to-Date $0.00
Percentage Paid 0%