2024 Mill and Overlay
Name 2024 Mill and Overlay
Date Updated 04-09-2024
Contact Kenny Khongmaly
Project Status Construction
Description This Project includes curb and gutter replacement, sidewalk replacement, full depth asphalt patching, pavement markings, and milling and asphalt overlay.
Status Details Curb and sidewalk replacement is currently underway on streets west of I-435 as well as the milling and overlay of the streets in the same area.  Below is the link to the current map of the 2024 Mill and Overlay streets.

https://cityofshawneeks.maps.arcgis.com/apps/instant/basic/index.html?appid=9482934c1c0446cd9c1037f415e778b0
Contact Phone 913-742-6267
Contact Email kkhongmaly@cityofshawnee.org
This Is a City Project
Number 3567
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm In House
Construction Contract McAnany Construction Inc.
Inspection Firm In House
Start Date 03-01-2024
Estimated End Date 12-01-2024
Budget Information
As of Feb 7 2024
Current Budget $6,702,937.35
Current Commitments $6,702,937.35
Paid-to-Date $6,698,691.00
Percentage Paid 99%