2024 Mill and Overlay
Name: 2024 Mill and Overlay
Date Updated: 11-22-2024
Contact: Kenny Khongmaly
Project Status: Construction
Description: This Project includes curb and gutter replacement, sidewalk replacement, full depth asphalt patching, pavement markings, and milling and asphalt overlay.
Status Details: All mill and overlay streets have been completed on this years contract.  The contractor is currently working on curb and sidewalk replacement is on miscellaneous areas around the City.
Below is the link to the current map of the 2024 Mill and Overlay streets.

https://cityofshawneeks.maps.arcgis.com/apps/instant/basic/index.html?appid=9482934c1c0446cd9c1037f415e778b0
Contact Phone: 913-742-6267
Contact Email: kkhongmaly@cityofshawnee.org
This Is a City Project:
Number: 3591
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: In House
Construction Contract: McAnany Construction Inc.
Inspection Firm: In House
Start Date: 03-01-2024
Estimated End Date: 12-01-2024
Budget Information
As of Jan 2 2025
Current Budget $7,948,560.00
Current Commitments $7,944,519.28
Paid-to-Date $7,943,817.00
Percentage Paid 99%