Monrovia Street (55th Street to Johnson Drive)
Name Monrovia Street (55th Street to Johnson Drive)
Date Updated 04-03-2024
Contact Jason DeWald, P.E.
Project Status Design
Description The Monrovia Street Improvement project is included on the City’s Capital Improvement Program (CIP) for construction in 2024. This project includes full removal and replacement of pavement, new curb and sidewalk, storm drainage improvements, ADA crossings at intersections, signing, and new lighting and pavement markings. 
Status Details Final plans are complete.  Construction is anticipated to begin early May.
Contact Phone 913-742-6234
Contact Email jdewald@cityofshawnee.org
This Is a City Project
Number 3561
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm HNTB Corporation
Construction Contract Amino Brothers
Inspection Firm HNTB Corporation
Start Date 03-13-2023
Estimated End Date 12-31-2024
Budget Information
As of Mar 6 2024
Current Budget $2,985,000.00
Current Commitments $627,791.00
Paid-to-Date $590,856.00
Percentage Paid 94%