Name: |
50th Street and Renee Drive CMP replacement |
Date Updated: |
10-31-2024 |
Contact: |
Arij Humeida, Project Manager |
Project Status: |
Construction |
Description: |
Replacement of eight pipes (approximately 1500 feet) and 9 inlets along 50th Street from Mullins Street to Summit Street plus the installation of 73 feet of new pipe and one new curb inlet. |
Status Details: |
Infrastructure Solutions LLC is the contractor. Construction is on time for completion. |
Contact Phone: |
913-742-6223 |
Contact Email: |
ahumeida@cityofshawnee.org |
This Is a City Project: |
|
Number: |
3578 |
This Is a Capital Improvement Project: |
|
Project Category: |
Drainage Improvements |
Design Firm: |
Renaissance Infrastructure Consultants |
Construction Contract: |
Infrastructure Solutions LLC |
Inspection Firm: |
Renaissance Infrastructure Consultants |
Start Date: |
07-29-2024 |
Estimated End Date: |
11-26-2024 |