71st & Midland CMP Replacement Project
Name 71st & Midland CMP Replacement Project
Date Updated 06-07-2023
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description This is replacement of a 66-inch pipe at the intersection of 71st St and Midland Dr. This project is a JCSMP 50:50 construction cost share project for 2022 SMP funds. 
Status Details Final Design and contract documents provided.  Advertised for Bid.  Bid opening (Virtual) scheduled for February 14, 2023 at 10am.  Construction Awarded at the February 27th City Council Meeting.  Preconstruction Meeting held on March 9th.

Construction rescheduled for July 15th to coordinate relocation/replacement of Evergy poles. 
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3552
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Affinis
Construction Contract Redford Construction
Inspection Firm Affinis
Start Date 03-09-2023
Estimated End Date 08-09-2023
Budget Information
As of May 3 2023
Current Budget $551,635.50
Current Commitments $551,635.50
Paid-to-Date $71,955.00
Percentage Paid 13%
Project Files