Name |
71st & Midland CMP Replacement Project |
Date Updated |
06-07-2023 |
Contact |
Ernie Longoria, P.E., PTOE |
Project Status |
Construction |
Description |
This is replacement of a 66-inch pipe at the intersection of 71st St and Midland Dr. This project is a JCSMP 50:50 construction cost share project for 2022 SMP funds. |
Status Details |
Final Design and contract documents provided. Advertised for Bid. Bid opening (Virtual) scheduled for February 14, 2023 at 10am. Construction Awarded at the February 27th City Council Meeting. Preconstruction Meeting held on March 9th.
Construction rescheduled for July 15th to coordinate relocation/replacement of Evergy poles. |
Contact Phone |
913-742-6312 |
Contact Email |
elongoria@cityofshawnee.org |
This Is a City Project |
|
Number |
3552 |
This Is a Capital Improvement Project |
|
Project Category |
Drainage Improvements |
Design Firm |
Affinis |
Construction Contract |
Redford Construction |
Inspection Firm |
Affinis |
Start Date |
03-09-2023 |
Estimated End Date |
08-09-2023 |