51st Place & Monticello (West) CMP Replacement Project
Name 51st Place & Monticello (West) CMP Replacement Project
Date Updated 12-30-2022
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description 51st Place and Monticello West includes the replacement of three pipes (394 LF) and three (3) structures. A 4th pipe non-eligible has been added as part of this system replacement. 
Status Details Construction bids were received in September. Project award is scheduled for October 10, 2022. Open excavation work is expected to occur in November and lining operations are expected to occur in February or March 2023.

Construction is expected to start in mid-November.

12/30/2022 UPDATE -
The full excavation pipe repair pipe has been completed. The remaining four pipes are to be rehabilitated by lining and   that work will be completed sequentially as pipes are cleaned, measured, liners made, liners resin impregnated and then installed. We anticipate that the final pipes will be completed by April 28, 2023. 
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3553
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson
Construction Contract Wiedenmann Inc.
Inspection Firm Olsson
Start Date 11-15-2022
Estimated End Date 04-28-2023
Budget Information
As of May 3 2023
Current Budget $311,000.00
Current Commitments $253,864.00
Paid-to-Date $235,398.00
Percentage Paid 92%