Barton Street - Johnson Drive to W. 60th Street
Name Barton Street - Johnson Drive to W. 60th Street
Date Updated 06-17-2022
Contact Cody Wilbers, P.E.
Project Status Design
Description This segment of Barton Street is an existing 2-lane residential ditch section street and is to be improved to current City standards. The City has recently completed reconstruction of other sections of streets within the area (59th Street, 59th Terrace, 60th Street, and King Street).  This project will be similar to those improved segments.
Status Details Walter P. Moore was selected as the engineering designer for the project.  They have completed preliminary plans for the stretch between 60th Street and 59th Terrace.  The goal will be to construct this stretch of Barton Street in late summer of 2022 and to construct the segment from 59th Terrace to Johnson Drive during 2023.
Contact Phone 913-742-6234
Contact Email cwilbers@cityofshawnee.org
This Is a City Project
Number 3542
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Walter P. Moore
Construction Contract TBD
Inspection Firm TBD
Start Date 07-25-2022
Estimated End Date 10-28-2022
Budget Information
As of Jun 2 2022
Current Budget $665,000.00
Current Commitments $163,750.00
Paid-to-Date $6,271.00
Percentage Paid 3%