ADA Sidewalk and Signal Improvements
Name ADA Sidewalk and Signal Improvements
Date Updated 01-06-2021
Contact Kevin Manning
Project Status Design
Description The City has secured federal Transportation Alternative (TA) funding to help improve pedestrian
connectivity at signalized intersections in accordance with Americans with Disability Act (ADA)
requirements. This project will include design at multiple intersections to add sidewalk facilities, signal
equipment, curb ramps and any other necessary features to improve pedestrian access and ensure
ADA compliance. 
Status Details Walter P. Moore has been selected as the design consultant.  Field check plans have been completed.  Office check plans will be completed in December 2020.  Project will be bid in March 2021 and will be constructed in the spring and summer of 2021.  
Contact Phone 913-742-6280
Contact Email kmanning@cityofshawnee.org
This Is a City Project
Number 3504
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Walter P. Moore
Construction Contract TBD
Inspection Firm TBD
Start Date 03-24-2020
Estimated End Date 11-12-2021
Budget Information
As of Jan 8 2021
Current Budget $600,000.00
Current Commitments $110,500.00
Paid-to-Date $65,561.00
Percentage Paid 59%