2020 Mill and Overlay Program
2020 Mill and Overlay Program
Name
2020 Mill and Overlay Program
Date Updated
01-06-2021
Contact
Kevin Manning
Project Status
Construction
Description
The 2020 Mill and Overlay Program will resurface approximately 41 lane miles of roads, in addition to replacing around 13 linear miles of curb and 4.5 linear miles of sidewalk.
Status Details
The City Council approved McAnany Construction as the low bidder on 2/10/20. The project is approximately 99% complete.
http://cityofshawneeks.maps.arcgis.com/apps/View/index.html?appid=870cd2d0de054578ac6ab2749483300d
Contact Phone
913-742-6280
Contact Email
kmanning@cityofshawnee.org
This Is a City Project
Number
3500
This Is a Capital Improvement Project
Project Category
Street Improvements
Design Firm
N/A
Construction Contract
2/10/2020
Inspection Firm
In-house
Start Date
03-02-2020
Estimated End Date
12-31-2020
Budget Information
As of Jan 8 2021
Current Budget
$5,812,500.00
Current Commitments
$5,810,391.03
Paid-to-Date
$5,495,602.00
Percentage Paid
94%