2020 Mill and Overlay Program
Name 2020 Mill and Overlay Program
Date Updated 01-06-2021
Contact Kevin Manning
Project Status Construction
Description The 2020 Mill and Overlay Program will resurface approximately 41 lane miles of roads, in addition to replacing around 13 linear miles of curb and 4.5 linear miles of sidewalk.  
Status Details The City Council approved McAnany Construction as the low bidder on 2/10/20.  The project is approximately 99% complete. 

http://cityofshawneeks.maps.arcgis.com/apps/View/index.html?appid=870cd2d0de054578ac6ab2749483300d
Contact Phone 913-742-6280
Contact Email kmanning@cityofshawnee.org
This Is a City Project
Number 3500
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm N/A
Construction Contract 2/10/2020
Inspection Firm In-house
Start Date 03-02-2020
Estimated End Date 12-31-2020
Budget Information
As of Jan 8 2021
Current Budget $5,812,500.00
Current Commitments $5,810,391.03
Paid-to-Date $5,495,602.00
Percentage Paid 94%