54th St & Flint St (McAnany Phase 2) Storm Drainage Improvements
Name:
54th St & Flint St (McAnany Phase 2) Storm Drainage Improvements
Date Updated:
07-27-2026
Contact:
Kirk Abbott
Project Status:
Future
Description:
The 54th Street and Flint Project will serve as a Phase 2 stormwater improvement that continues the McAnany project by conveying stormwater from McAnany Drive to the existing system at 54th Street and Flint Street.
The project will include:
- new reinforced concrete pipe (RCP) and storm inlets along some rear property lines as well as 53rd Terrace and Flint Street.
- New and replacement curb, along with mill and overlay improvements
- Streetlight improvements on 53rd Terrace and Flint St to 54th St.
- Grading to accommodate future sidewalk construction at a later date.
This project would be funded entirely by the City of Shawnee through the Parks and Pipes Fund and General Fund.
Status Details:
Scope and Fee negotiations with selected firm. Anticipate council award August 24th, 2026.
Contact Phone:
913-742-6231
Contact Email:
kabbott@cityofshawnee.org
This Is a City Project:
Number:
3657
This Is a Capital Improvement Project:
Project Category:
Drainage Improvements
Design Firm:
TBD
Construction Contract:
TBD
Inspection Firm:
TBD
Start Date:
08-24-2026
Estimated End Date:
03-31-2028
Budget Information
As of Jul 1 2026
Current Budget
$0.00
Current Commitments
$0.00
Paid-to-Date
$0.00
Percentage Paid
0%