Shawnee Mission Parkway - I-435 to K-7
Name: Shawnee Mission Parkway - I-435 to K-7
Date Updated: 10-07-2025
Contact: Kirk Abbott
Project Status: Approved
Description: This project will include mill and overlay, replacement of deteriorated curb and sidewalk, pavement markings, storm drainage facilities, adding a signal at Vista and SMP and other appurtenant works.
Status Details: October: Paving completed from I-435 to Lackman.  Anticipated striping to be complete early in the month.

Mill will continue early in the month from I-435 towards Vista Dr.  Pavement repairs will be conducted before paving. Paving expected to be complete by mid-October.

Milling will start from Vista Dr to the project limit just past K-7. Followed by pavement repairs and paving.

New right turn lane at Woodland Dr is complete. Pavement work and striping repairs pending.  

Storm water replacement work continues mostly between Vista Dr and K-7. 
Contact Phone: 913-742-6231
Contact Email: kabbott@cityofshawnee.org
This Is a City Project:
Number: 3610
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: BG Consultants
Construction Contract: Superior Bowen Asphalt Company, LLC
Inspection Firm: City
Start Date: 08-04-2025
Estimated End Date: 03-31-2026
Budget Information
As of Sep 3 2025
Current Budget $9,200,000.00
Current Commitments $8,325,234.75
Paid-to-Date $524,067.00
Percentage Paid 6%
Project Files
File Name
Download
PN3610_SMPKWY_IFC PLANS_Forwebsite.pdf
Project Images
File Name
View
Download
Paving east of Vista Dr north side 091025.jpg
Overlay WB inside Ln At St 242.jpg
Paving South Turn Ext @ Vista 100125.jpg