2020 Stormwater Pipe Repair Project
Name 2020 Stormwater Pipe Repair Project
Date Updated 06-29-2020
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description Olsson Associates and city staff have completed initial repair site location maps and they are attached. These repair projects are to repair stormwater pipes and structures in advance of the 2020 Mill & Overlay Street project.  
Status Details 12/12/19:  Final Plans are on the 12/12/2019 City Council agenda for approval and authorization to advertise for construction bids. Project notification letters are being sent to adjacent property owners with the appropriate repair map attached. Staff plans to bid the project in December. 

2/24/20 UPDATE:  There are 36 different repair locations on this project. The stormwater pipe repair project started on 2/03/20. The pipe repairs are scheduled to take place from the west side of Shawnee to the east side of Shawnee. Please view the PDF Maps for specific information about individual locations:
       In Progress -                   Maps 2, 5, 7, 9, Alt 2 & 11
       Substantially Complete - Maps 1,3,4 & Alt 11

3/27/20 UPDATE:  The 2020 Stormwater Pipe Repair Project is 50% complete. The contractor has most of the locations west of I-435 complete, except for restoration and pipe lining. Please view the PDF Maps for specific information about individual locations:
       In Progress -                    Maps 5, 7, 12, and 18.
       Substantially Complete - Maps 1, 2, 3,4, 6, 9, 10, 11, 13, 14, 15, Alt 2, Alt 6 and Alt 11.

4/27/20 UPDATE:  The 2020 Stormwater Pipe Repair Project is 75% complete.  Please view the PDF Maps for specific information about individual locations:
      In Progress -                    Maps 5, 7, 8, 12, 16, 17, 18, 19, Alt 1 and Alt 4.
      Substantially Complete - Maps 1, 2, 3,4, 6, 9, 10, 11, 13, 14, 15, 20, Alt 2, Alt 6, Alt 11 and Alt 12.

5/27/20 UPDATE:  The 2020 Stormwater Pipe Repair Project is 80% complete. Please view the PDF Maps for specific information about individual locations:
     In Progress -                    Maps 7, 8, 16, 17, 19, 21 Alt 1, Alt 7 and Alt 8.
     Work Not Started -          Map 23, 24, 25, Alt 13 and Alt 26.
     Substantially Complete - Maps 1, 2, 3, 4, 5, 6, 9, 10, 11, 12, 13, 14, 15, 18, 20, Alt 2,    Alt 4, Alt 6, Alt 11 and Alt 12.
    
6/29/20 UPDATE:  The 2020 Stormwater Pipe Repair Project is substantially complete.  All pipe repairs and pipe lining were completed by 6/26/20.  Items incidental to the pipe repair work such as fence and sod installation, are still in progress. All locations not sodded by May 15, 2020, will be sodded in the fall, starting in late September. 
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3491
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson 
Construction Contract Wiedenmann, Inc.
Inspection Firm Olsson and City Staff
Start Date 12-23-2019
Estimated End Date 06-26-2020
Budget Information
As of Jun 3 2020
Current Budget $1,437,972.19
Current Commitments $1,437,972.19
Paid-to-Date $846,158.00
Percentage Paid 58%
Project Notices
File Name
Download
Maps Combined 02.24.20.pdf
PROJECT LOCATION MAP.pdf
Project Images
File Name
View
Download
IMG_2104.jpg
IMG_2092.jpg
IMG_1750.jpg
IMG_2071.jpg
IMG_2041.jpg
IMG_1806.jpg
IMG_2709.jpg
thumbnail_IMG_3126.jpg
IMG_2091.jpg
IMG_2129.jpg
thumbnail_IMG_2924.jpg
thumbnail_IMG_3138.jpg
thumbnail_IMG_3288.jpg
IMG_2128.jpg
IMG_2435.jpg