75th Street Corridor Improvement Project - Switzer to Quivira
Name 75th Street Corridor Improvement Project - Switzer to Quivira
Date Updated 05-03-2023
Contact Loren Snyder, P.E.
Project Status Construction
Description The project consists of intersection modifications and geometric improvements at 75th and Quivira and 75th and Nieman, mill and overlay of the corridor, replacement of curb, sidewalk, storm sewer, street lighting and additional streetscaping and beautification efforts throughout. 
Status Details Construction of the Re-Imagine 75th Street Project started on March 21, 2022 and is at substantial completion.

Two items will occur in the Spring of next year, placement of decorative crosswalks at the major intersections and the completion of staining and painting of the concrete walls.

Contact Phone 913-742-6229
Contact Email lsnyder@cityofshawnee.org
This Is a City Project
Number 3481
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Transystems 
Construction Contract Miles Excavating
Inspection Firm GBA 
Start Date 03-21-2022
Estimated End Date 12-09-2022
Budget Information
As of May 3 2023
Current Budget $6,350,000.00
Current Commitments $6,251,208.44
Paid-to-Date $6,174,294.00
Percentage Paid 98%