75th Street Corridor Improvement Project - Switzer to Quivira
Name 75th Street Corridor Improvement Project - Switzer to Quivira
Date Updated 06-17-2022
Contact Cody Wilbers, P.E.
Project Status Construction
Description The project consists of intersection modifications and geometric improvements at 75th and Quivira and 75th and Nieman, mill and overlay of the corridor, replacement of curb, sidewalk, storm sewer, street lighting and additional streetscaping and beautification efforts throughout. 
Status Details Construction of the Re-Imagine 75th Street Project started on March 21, 2022.  

They are currently working on the north side of 75th Street between Nieman and Quivira and on the south side between Switzer and Nieman.   There will be several intermittent lane and side road closures along the both sides of the road the next couple months.  You'll see work on the storm sewer, sidewalk, curb and gutter, signals, driveways, side streets and other miscellaneous items along the corridor over the next several months.

The lighting along the corridor will be replaced with the project and with that, the street lights will not be operating for stretches at a time. 


Contact Phone 913-742-6234
Contact Email cwilbers@cityofshawnee.org
This Is a City Project
Number 3481
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Transystems 
Construction Contract Miles Excavating
Inspection Firm GBA 
Start Date 03-21-2022
Estimated End Date 09-17-2022
Budget Information
As of Jun 2 2022
Current Budget $6,350,000.00
Current Commitments $6,189,160.42
Paid-to-Date $1,628,728.00
Percentage Paid 26%