71st Street Sidewalk Improvements 
Name 71st Street Sidewalk Improvements 
Date Updated 08-30-2019
Contact Kevin Manning
Project Status Design
Description This project will add sidewalk on portions of 71st Street to provide for better pedestrian access to Erfurt Park.  
Status Details Final plans are scheduled to go to the Governing Body for approval on October 14, 2019.  Construction should start October 21, 2019 and be complete by December 31st, 2019.  
Contact Phone 913-742-6280
Contact Email kmanning@cityofshawnee.org
This Is a City Project
Number 3472
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Olsson
Construction Contract TBD
Inspection Firm In-house
Start Date 09-19-2018
Estimated End Date 12-31-2019
Project Notices
File Name
Download
71st Street Sidewalk Improvements_08-14-2019.pdf
Project Images
File Name
View
Download
No images to show...
Silk UI Framework Simulation Device
Resize the window to preview the page in target devices.
Open the settings to change the simulation device options.