Quivira Drive and Park Street - Storm Drainage Improvements
Name Quivira Drive and Park Street - Storm Drainage Improvements
Date Updated 11-06-2019
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description Two (2) 91” x 144” corrugated metal arch pipes (CMAP) culverts have reached the end of their service life and need to be replaced or relined. Inspections have also indicated that adjacent metal pipe is also at the end of their service life and needs to also be relined or replaced.  The design consultant will analyze alternatives and survey upstream and downstream from the culverts to ensure that construction will tie into existing City floodplain limits.
Status Details The contractor completed both ends of the replacement culvert on Quivira Drive and is backfilling to final grade.  Installation of curb and gutter and asphalt is planned for the week of November 11th.  Work commenced to replace the pipe at the Park Street entrance and the crossing is anticipated to be completed this week. (11-6-19)
Contact Phone 913.742.6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3466
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Renaissance Infrastructure Consulting, Inc.
Construction Contract Kissick Construction Company
Inspection Firm Renaissance Infrastructure Consulting, Inc.
Start Date 10-23-2018
Estimated End Date 12-15-2019
Project Notices
File Name
Download
Quivira Drive Detour Route.PNG
Project Images
File Name
View
Download
20181004_160233.jpg
20181004_160244.jpg
20181004_160337.jpg
20181004_160359.jpg
20181004_160701.jpg
20181004_160802.jpg
20181004_160851.jpg
Silk UI Framework Simulation Device
Resize the window to preview the page in target devices.
Open the settings to change the simulation device options.