Johnson Drive & Widmer Street - Storm Drainage Improvements
Name Johnson Drive & Widmer Street - Storm Drainage Improvements
Date Updated 05-06-2020
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description 780 LF of 72” x 102” corrugated metal arch pipe (CMAP) beneath Johnson Drive is at the end of its service life and will be relined or replaced.  The design consultant will also analyze options to determine if the culvert can be upsized to prevent overtopping of
Johnson Dr in the 1% chance event.  Inspections of adjacent metal pipes also revealed that they are also at the end of their service life and will also need to be relined or replaced.
Status Details All storm lines have been installed and endsection handrails and riprap has been placed.  The Contractor is beginning restoration.  Restoration is expected to be completed in May and project closeout is underway (5-6-20). 
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3460
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson Associates, Inc.
Construction Contract VF Anderson Builders, LLC
Inspection Firm Olsson
Start Date 10-23-2018
Estimated End Date 05-30-2020
Budget Information
As of Jun 3 2020
Current Budget $2,133,000.00
Current Commitments $1,722,732.70
Paid-to-Date $1,620,472.00
Percentage Paid 94%