| Name: |
McAnany Drive - Nieman Road to Lucille Lane Street Improvement Project |
| Date Updated: |
07-27-2026 |
| Contact: |
Kirk Abbott |
| Project Status: |
Construction |
| Description: |
This segment of McAnany Drive is a flat, narrow section with limited sidewalks, street lighting, and proper drainage facilities. This project will include full removal and replacement of pavement, new curb and sidewalk, storm drainage improvements, ADA crossings at intersections, signing, new pavement markings, and LED streetlight luminaires. Staff is ready to proceed with the design of this project. Construction is anticipated to be completed by early 2027. Construction will require temporary detours and lane closures. |
| Status Details: |
Construction will begin the first week of August. Some preliminary work will begin in late July include tree removal and utility investigation work.
A final open house meeting was on Wednesday July 22 at City Hall between 5 and 6.30pm.
This project is planned to be constructed by early 2027, weather permitting. |
| Contact Phone: |
913-742-6231 |
| Contact Email: |
kabbott@cityofshawnee.org |
| This Is a City Project: |
|
| Number: |
3609 |
| This Is a Capital Improvement Project: |
|
| Project Category: |
Street Improvements |
| Design Firm: |
Walter P. Moore and Associates, Inc. |
| Construction Contract: |
Infrastructure Solutions |
| Inspection Firm: |
City |
| Start Date: |
11-13-2024 |
| Estimated End Date: |
02-26-2027 |