McAnany Drive - Nieman Road to Lucille Lane Street Improvement Project
Name: McAnany Drive - Nieman Road to Lucille Lane Street Improvement Project
Date Updated: 05-19-2026
Contact: Kirk Abbott
Project Status: Design
Description: This segment of McAnany Drive is a flat, narrow section with limited sidewalks, street lighting, and proper drainage facilities. This project will include full removal and replacement of pavement, new curb and sidewalk, storm drainage improvements, ADA crossings at intersections, signing, new pavement markings, and LED streetlight luminaires. Staff is ready to proceed with the design of this project. Construction is anticipated to be completed by early 2027. Construction will require temporary detours and lane closures.
Status Details: - Utility relocation work is complete.
- Bids have been received for construction and are in review.
- City council award of construction contract expected June 8th.
- Construction is anticipated to begin in June/July of 2026.
- This project is planned to be constructed by early 2027.

A final public meeting is anticipated for before construction starts. 
Contact Phone: 913-742-6231
Contact Email: kabbott@cityofshawnee.org
This Is a City Project:
Number: 3609
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: Walter P. Moore and Associates, Inc.
Construction Contract: TBD
Inspection Firm: City 
Start Date: 11-13-2024
Estimated End Date: 02-26-2027
Budget Information
As of May 11 2026
Current Budget $2,864,100.00
Current Commitments $488,304.88
Paid-to-Date $433,271.00
Percentage Paid 88%
Project Files
File Name
Download
3609 - IFB-McAnany Drive Street Impr Project-SealedPlans-reduced.pdf
Overall_Project_Exhibit.pdf
Public Meeting 1 Presentation Slides.pdf
Project Images
File Name
View
Download
No images to show...