McAnany Drive - Nieman Road to Lucille Lane Street Improvement Project
Name: McAnany Drive - Nieman Road to Lucille Lane Street Improvement Project
Date Updated: 07-27-2026
Contact: Kirk Abbott
Project Status: Construction
Description: This segment of McAnany Drive is a flat, narrow section with limited sidewalks, street lighting, and proper drainage facilities. This project will include full removal and replacement of pavement, new curb and sidewalk, storm drainage improvements, ADA crossings at intersections, signing, new pavement markings, and LED streetlight luminaires. Staff is ready to proceed with the design of this project. Construction is anticipated to be completed by early 2027. Construction will require temporary detours and lane closures.
Status Details: Construction will begin the first week of August.  Some preliminary work will begin in late July include tree removal and utility investigation work.

A final open house meeting was on Wednesday July 22 at City Hall between 5 and 6.30pm.

This project is planned to be constructed by early 2027, weather permitting. 
Contact Phone: 913-742-6231
Contact Email: kabbott@cityofshawnee.org
This Is a City Project:
Number: 3609
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: Walter P. Moore and Associates, Inc.
Construction Contract: Infrastructure Solutions
Inspection Firm: City 
Start Date: 11-13-2024
Estimated End Date: 02-26-2027
Budget Information
As of Aug 5 2026
Current Budget $3,160,963.00
Current Commitments $3,031,162.88
Paid-to-Date $451,400.00
Percentage Paid 14%
Project Files
File Name
Download
3609 - IFB-McAnany Drive Street Impr Project-SealedPlans-reduced.pdf
Overall_Project_Exhibit.pdf
Project Images
File Name
View
Download
No images to show...