Name |
50th Street and Rene Street CMP Replacement |
Date Updated |
03-05-2024 |
Contact |
Ernie Longoria, P.E., PTOE |
Project Status |
Design |
Description |
Replacement of eight pipes (approximately 1500 feet) and 9 inlets along 50th Street from Mullins Street to Summit Street plus installation of 73 feet of new pipe and one new curb inlet. |
Status Details |
RIC is working on final plans. Working on tract maps for easement acquisition.
Public meeting held on February 15, 2024 in the Council Chambers from 6pm-7pm |
Contact Phone |
913-742-6312 |
Contact Email |
elongoria@cityofshawnee.org |
This Is a City Project |
|
Number |
3578 |
This Is a Capital Improvement Project |
|
Project Category |
Drainage Improvements |
Design Firm |
RIC |
Construction Contract |
TBD |
Inspection Firm |
RIC |
Start Date |
09-26-2023 |
Estimated End Date |
09-26-2024 |