50th Street and Rene Street CMP Replacement
Name 50th Street and Rene Street CMP Replacement
Date Updated 03-05-2024
Contact Ernie Longoria, P.E., PTOE
Project Status Design
Description Replacement of eight pipes (approximately 1500 feet) and 9 inlets along 50th Street from Mullins Street to Summit Street plus installation of 73 feet of new pipe and one new curb inlet.
Status Details RIC is working on final plans.  Working on tract maps for easement acquisition. 

Public meeting held on February 15, 2024 in the Council Chambers from 6pm-7pm
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3578
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm RIC
Construction Contract TBD
Inspection Firm RIC
Start Date 09-26-2023
Estimated End Date 09-26-2024
Budget Information
As of Mar 6 2024
Current Budget $2,192,840.00
Current Commitments $269,920.00
Paid-to-Date $61,072.00
Percentage Paid 22%
Project Files