Quivira Road (Shawnee Mission Parkway to 75th Street)
Name: Quivira Road (Shawnee Mission Parkway to 75th Street)
Date Updated: 04-02-2025
Contact: Jason DeWald, P.E.
Project Status: Construction
Description: The Quivira Road Rehabilitation Project from Shawnee Mission Parkway to 75th Street is included on the City's Capital Improvement Program for construction in 2024 and has been approved for partial County Assistance Road System (CARS) Funding. This project is approximately 1.5 miles in length and will include a mill and overlay of the current roadway, storm drainage improvements, street lights, fiber, pavement markings, and upgrades and repairs to ADA ramps, curbs, sidewalk, and drives.
Status Details: Project is complete. 
Contact Phone: 913-742-6234
Contact Email: jdewald@cityofshawnee.org
This Is a City Project:
Number: 3560
This Is a Capital Improvement Project:
Project Category: Street Improvements
Design Firm: Olsson, Inc
Construction Contract: VF Anderson
Inspection Firm: Olsson, Inc
Start Date: 05-22-2023
Estimated End Date: 12-31-2024
Budget Information
As of Apr 2 2025
Current Budget $4,720,142.54
Current Commitments $4,710,117.00
Paid-to-Date $4,646,760.00
Percentage Paid 98%