79th & Switzer CMP Replacement Project
Name 79th & Switzer CMP Replacement Project
Date Updated 06-07-2023
Contact Ernie Longoria, P.E., PTOE
Project Status Design
Description This is replacement of a 675 LF of 72"x120" CMAP in the industrial SE corner of Shawnee. This project is JCSMP 50:50 construction cost share project. 
Status Details Consultant has finished final design.  Working on contract documents, bid advertisement, easement acquisition.  Bid opening scheduled for February 17, 2023.  Construction award at March 13th City Council meeting.

Construction mobilization planned for the week of June 5, 2023.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3551
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Renaissance Infrastructure Consulting
Construction Contract VF Anderson Builders, Inc.
Inspection Firm Renaissance Infrastructure Consulting
Start Date 05-09-2023
Estimated End Date 10-31-2023
Budget Information
As of May 3 2023
Current Budget $1,800,000.00
Current Commitments $196,864.50
Paid-to-Date $131,093.00
Percentage Paid 66%