64th & Chouteau CMP Replacement Project
Name 64th & Chouteau CMP Replacement Project
Date Updated 12-30-2022
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description This is replacement of a 96-inch pipe in rear yards of Chouteau between 64th St and 64th Terr plus 2 additional pipes south of 64th Ter. This project is a JCSMP 50:50 construction cost share project for 2022 SMP funds. 
Status Details Vortex Lining has been awarded the construction project and the Geopolymer repair option was selected.  The Pre-Construction Meeting was held in December and Vortex Lining expects to start work in late January. 
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3549
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm CDM Smith
Construction Contract Vortex Lining, LLC
Inspection Firm CDM
Start Date 12-05-2022
Estimated End Date 06-09-2023
Budget Information
As of May 3 2023
Current Budget $2,703,000.00
Current Commitments $1,463,545.00
Paid-to-Date $176,286.00
Percentage Paid 12%
Project Files
File Name
Download
64th_Chouteau_BidContractSpec_09302022.pdf
CIPP.pdf
Geopolymer.pdf
Replacement.pdf
Spirolite.pdf
Project Images
File Name
View
Download
No images to show...