2022 - Stormwater Pipe Repair Project
Name 2022 - Stormwater Pipe Repair Project
Date Updated 12-30-2022
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description This stormwater project will remove and replace or cure-in-place line failing pipes at 33 locations throughout the City - see attached Maps for locations. Funding for this infrastructure repair  project is through the Stormwater Utility Fund. The fund is comprised of fees that are paid by every property owner in Shawnee.

In general, this annual project focuses on repairing pipes beneath roads scheduled for the annual pavement mill and overlay project or failed pipes that have resulted in sinkholes in resident's yards. 
Status Details Final Repair Maps for the 2022 project are completed. Project notices and Access Agreements are being sent to affected residents during the first week of November.  Final Plan Approval to bid the project for construction is on the November 8, 2021 City Council Agenda. 


02/24/2022 UPDATE: The below noted Maps are under construction. Approximately 5% of the work is in various construction phases.

   In Progress - Maps Alt 5.
   Substantially Complete - Maps 2 & 4.
   Completed - Map Alt 9.
 

04/18/2022 UPDATE: The below noted Maps are under construction. Approximately 10% of the work is in various construction phases.

   Substantially Complete - Maps 2, 4 and Alt 5.
   Completed - Map 7 & Alt 9.


06/08/2022 UPDATE: The below noted Maps are under construction. Approximately 40% of the work is in various construction phases.

   Completed - Maps 2, 7, 14, 16 & Alt 9.
   Substantially Complete - Maps 4. 9, 27 & Alt 5.
   In Progress - Maps 5, 23, & Alt 5.  
   Starting Soon - Maps 3, 6, 8, 10, 11, 12, 13, 17, 18, 26 & Alt 13.

08/22/22 UPDATE: The below noted Maps are under construction. Approximately 70% of the work is in various construction phases.

   Completed - Maps 2, 7, 14, 16 19, Alt 9 & Alt 9.
   Substantially Complete - Maps 4. 5, 8, 9, 21, 22, 27, 28, Alt 2, Alt 5, Alt 6, & Alt 8.
   In Progress - Maps 3, 6, 11, 17, 23 & 29.  
   Starting Soon - Maps 1, 10, 12, 13, 15, 18, 24, 25, 26, 30 & Alt 4.

9-30-2022 UPDATE - Map 1 is starting on 10/2/2022 and 63rd and Lackman area should be completed this week. Two additional locations are scheduled for lining operations on 10/17 and 10/18. Completed areas should start receiving sod on 10/3 and be completed by the end of October.

11-2-2022 UPDATE -
This project including final sodding is expected to be completed by 11-11-22. One final added location near Shawnee Mission Parkway and Woodland has not been started yet but is expected to be completed by 12-2-2022,

12/20-2022 UPDATE -
The contractor has only 1 final pipe to line and is working on the final punch list items. 
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3531
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson Associates
Construction Contract InfraStructure Solutions LLC
Inspection Firm Olsson Associates
Start Date 01-03-2022
Estimated End Date 01-31-2023
Budget Information
As of May 3 2023
Current Budget $1,893,910.00
Current Commitments $1,893,910.00
Paid-to-Date $1,650,379.00
Percentage Paid 87%