2021 Stormwater Pipe Repair - West
Name 2021 Stormwater Pipe Repair - West
Date Updated 05-27-2022
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description This stormwater project will remove and replace or cure in place (line) 35-50 failing pipes, at up to 35 locations, throughout the City - see attached pdf Maps for locations. Funding for this infrastructure repair project is through a one-time allocation from the General Fund. 
Status Details Restoration is underway and the contractor will restart work the week of June 6th.  Six sites remain on the work plan.  Map 8 will be completed later this year.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3529
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm BHC Rhodes
Construction Contract Wiedenmann Inc.
Inspection Firm BHC Rhodes
Start Date 01-03-2022
Estimated End Date 09-30-2022
Budget Information
As of Jun 2 2022
Current Budget $1,851,888.00
Current Commitments $1,638,586.50
Paid-to-Date $415,205.00
Percentage Paid 25%