2021 Stormwater Pipe Repair Project - East
Name 2021 Stormwater Pipe Repair Project - East
Date Updated 12-30-2022
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description This stormwater project will remove and replace or cure in place (line) 35-50 failing pipes, at up to 35 locations, throughout the City - see attached pdf Maps for locations. Funding for this infrastructure repair project is through a one-time allocation from the General Fund.

Status Details The 2021 Pipe Repair Project -EAST was awarded to Infrastructure Solutions LLC, on June 28, 2021, in the amount of $1,651,149.00. The contract includes location Maps 1-21, 23-25 and Alt 1-11.  Please see attached Map Locations for reference.

The Notice to Proceed was issued on July 26, 2021.
The anticipated Contract Completion date is March 13, 2022.

   Phase 1 (August - October): 
     MAPS 1, 8, 9, 10, 12, 13, 17, 18, 19 & 21. 
     MAP ALTs 5, 7 & 11.

   Phase 2 (November - December): 
     MAPS 2, 3, 4, 5, 6, 8, 11, 14 A&B, 15, 16, 20, 22, 23, 24 & 25.
     MAPS ALTs 1, 2, 3, 4, 6, 8, 9 & 10


08./24/21 UPDATE:  The below noted Maps are under construction and approximately 10% of the work is in various construction phases.
   
   In Progress - Maps 5, 8, 18, 21, Alt 1 & Alt 7.
   Completed - Map 24


09/08/21 UPDATE:  The below noted Maps are under construction. Approximately 15% of the work is in various construction phases.

   In Progress - Maps 8, 11, 18, & Alt 1
   Substantially Complete - Maps 1, 19, 21, 26, Alt 4, Alt 5 & Alt 7
   Completed - Maps 5, 20 & 24


11/2/2021 UPDATE: The below noted Maps are under construction. Approximately 25% of the work is in various construction phases.

   In Progress - Maps 2, 4, 9, 10, 11, 18, & Alt 1
   Substantially Complete - Maps 1, 5, 8, 17, 19, 20, 21, 26, Alt 4, Alt 5 & Alt 7
   Completed - Map 24


11/30/2021 UPDATE: The below noted Maps are under construction. Approximately 50% of the work is in various construction phases.

   In Progress - Maps 2, 4, 9, 10, 18, 23 & Alt 1.
   Substantially Complete - Maps 1, 5, 8, 11, 17, 21, 26, Alt 4, Alt 5 & Alt 7,
   Completed - Map 24 


01/19/2022 UPDATE: The below noted Maps are under construction. Approximately 55% of the work is in various construction phases.

   In Progress - Maps 2, 4, 9, 10, 12, 13, 14, 18, Alt 3 & Alt 8.
   Substantially Complete - Maps 1, 5, 8, 11, 15, 16, 23, 26, Alt 4, Alt 5 & Alt 7,
   Completed - Map 3 , 6, 17, 19, 20, 21, 24, 25,  Alt 1 & Alt 2.

03/02/2022 UPDATE: The below noted Maps are under construction. Approximately 60% of the work is in various construction phases.

   In Progress - Maps 2, 4, 7, 9, 10, 12, 13, 18, Alt 3 & Alt 6.
   Substantially Complete - Maps 1, 5, 8, 11, 14, 15, 16, 23, 26, Alt 4, Alt 5 & Alt 7,
   Completed - Map 3, 6, 17, 19, 20, 21, 24, 25,  Alt 1 & Alt 2.
   Starting Soon: Map Alt 8 & Alt 9.


04/18/22 UPDATE:  The below noted Maps are under construction. Approximately 65% of the work is in various construction phases.

In Progress - Maps  4, 9, 13, 18 & Alt 3.
   Substantially Complete - Maps 1, 2, 5,, 7, 8, 10, 11, 12, 14, 15, 16, 23, 26, Alt 4, Alt 5 & Alt 7.
   Completed - Map 3, 6, 17, 19, 20, 21, 24, 25,  Alt 1 & Alt 2.
  

06/08/22 UPDATE:  The below noted Maps are under construction. Approximately 80% of the work is in various construction phases.

   In Progress - Maps  9, 18 & Alt 11.
   Substantially Complete - Maps 1, 5, 7, 8, 10, 11, 12, 13, 14, 15, 16, 23, 26, Alt 3, Alt 4, Alt 5 , Alt 6, Alt 7,
   Alt 8 , Alt 9 & Alt 10.
   Completed - Map 2, 3, 6, 17, 19, 20, 21, 24, 25,  Alt 1 & Alt 2.

08/22/22 UPDATE:  The below noted Maps are under construction. Approximately 90% of the work is in various construction phases.

   In Progress - Maps  4 & 18
   Substantially Complete - Maps 1, 9, 10,  23, 26, Alt 3, Alt 5 , Alt 6, Alt 8, Alt 9, Alt 10 & Alt 11.
   Completed - Map 2, 3, 5, 6, 7, 8, 11, 12, 13, 14, 15, 16, 17, 19, 20, 21, 24, 25, Alt 1,   Alt 2, Alt 4, & Alt 7.

9-30-2022 UPDATE -
All locations except Map 4 are completed and sod is to start on 10/3/2022 and continue until all locations have received sod.

11-2-2022 UPDATE:
The project is complete except for final punch list items.

12/30/2022 UPDATE -
Project is complete and is working on final clean-up corrections.
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3530
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson Associates
Construction Contract InfraStructure Solutions LLC
Inspection Firm Olsson Associates
Start Date 07-26-2021
Estimated End Date 01-20-2023
Budget Information
As of May 3 2023
Current Budget $1,790,042.00
Current Commitments $1,714,662.50
Paid-to-Date $1,711,222.00
Percentage Paid 99%
Project Files
File Name
Download
21.8.23.2021.PR.East.UPDATED.UPLOADED to Website.pdf
Project Images
File Name
View
Download
No images to show...