Status Details |
The 2021 Pipe Repair Project -EAST was awarded to Infrastructure Solutions LLC, on June 28, 2021, in the amount of $1,651,149.00. The contract includes location Maps 1-21, 23-25 and Alt 1-11. Please see attached Map Locations for reference.
The Notice to Proceed was issued on July 26, 2021. The anticipated Contract Completion date is March 13, 2022.
Phase 1 (August - October): MAPS 1, 8, 9, 10, 12, 13, 17, 18, 19 & 21. MAP ALTs 5, 7 & 11.
Phase 2 (November - December): MAPS 2, 3, 4, 5, 6, 8, 11, 14 A&B, 15, 16, 20, 22, 23, 24 & 25. MAPS ALTs 1, 2, 3, 4, 6, 8, 9 & 10
08./24/21 UPDATE: The below noted Maps are under construction and approximately 10% of the work is in various construction phases. In Progress - Maps 5, 8, 18, 21, Alt 1 & Alt 7. Completed - Map 24
09/08/21 UPDATE: The below noted Maps are under construction. Approximately 15% of the work is in various construction phases.
In Progress - Maps 8, 11, 18, & Alt 1 Substantially Complete - Maps 1, 19, 21, 26, Alt 4, Alt 5 & Alt 7 Completed - Maps 5, 20 & 24
11/2/2021 UPDATE: The below noted Maps are under construction. Approximately 25% of the work is in various construction phases.
In Progress - Maps 2, 4, 9, 10, 11, 18, & Alt 1 Substantially Complete - Maps 1, 5, 8, 17, 19, 20, 21, 26, Alt 4, Alt 5 & Alt 7 Completed - Map 24
11/30/2021 UPDATE: The below noted Maps are under construction. Approximately 50% of the work is in various construction phases.
In Progress - Maps 2, 4, 9, 10, 18, 23 & Alt 1. Substantially Complete - Maps 1, 5, 8, 11, 17, 21, 26, Alt 4, Alt 5 & Alt 7, Completed - Map 24
01/19/2022 UPDATE: The below noted Maps are under construction. Approximately 55% of the work is in various construction phases.
In Progress - Maps 2, 4, 9, 10, 12, 13, 14, 18, Alt 3 & Alt 8. Substantially Complete - Maps 1, 5, 8, 11, 15, 16, 23, 26, Alt 4, Alt 5 & Alt 7, Completed - Map 3 , 6, 17, 19, 20, 21, 24, 25, Alt 1 & Alt 2.
03/02/2022 UPDATE: The below noted Maps are under construction. Approximately 60% of the work is in various construction phases.
In Progress - Maps 2, 4, 7, 9, 10, 12, 13, 18, Alt 3 & Alt 6. Substantially Complete - Maps 1, 5, 8, 11, 14, 15, 16, 23, 26, Alt 4, Alt 5 & Alt 7, Completed - Map 3, 6, 17, 19, 20, 21, 24, 25, Alt 1 & Alt 2. Starting Soon: Map Alt 8 & Alt 9.
04/18/22 UPDATE: The below noted Maps are under construction. Approximately 65% of the work is in various construction phases.
In Progress - Maps 4, 9, 13, 18 & Alt 3. Substantially Complete - Maps 1, 2, 5,, 7, 8, 10, 11, 12, 14, 15, 16, 23, 26, Alt 4, Alt 5 & Alt 7. Completed - Map 3, 6, 17, 19, 20, 21, 24, 25, Alt 1 & Alt 2.
06/08/22 UPDATE: The below noted Maps are under construction. Approximately 80% of the work is in various construction phases.
In Progress - Maps 9, 18 & Alt 11. Substantially Complete - Maps 1, 5, 7, 8, 10, 11, 12, 13, 14, 15, 16, 23, 26, Alt 3, Alt 4, Alt 5 , Alt 6, Alt 7, Alt 8 , Alt 9 & Alt 10. Completed - Map 2, 3, 6, 17, 19, 20, 21, 24, 25, Alt 1 & Alt 2.
08/22/22 UPDATE: The below noted Maps are under construction. Approximately 90% of the work is in various construction phases.
In Progress - Maps 4 & 18 Substantially Complete - Maps 1, 9, 10, 23, 26, Alt 3, Alt 5 , Alt 6, Alt 8, Alt 9, Alt 10 & Alt 11. Completed - Map 2, 3, 5, 6, 7, 8, 11, 12, 13, 14, 15, 16, 17, 19, 20, 21, 24, 25, Alt 1, Alt 2, Alt 4, & Alt 7.
9-30-2022 UPDATE - All locations except Map 4 are completed and sod is to start on 10/3/2022 and continue until all locations have received sod.
11-2-2022 UPDATE: The project is complete except for final punch list items.
12/30/2022 UPDATE - Project is complete and is working on final clean-up corrections. |