49th and Quivira Stormwater CMP Replacement Project, P.N. 
Name 49th and Quivira Stormwater CMP Replacement Project, P.N. 
Date Updated 06-08-2022
Contact Cynthia Moeller-Krass, P.E.
Project Status Construction
Description A storm drainage project is scheduled to take place just west of Quivira from 49th Place through 49th Street. The project will remove and replace an existing failing 18-36" corrugated metal  stormwater pipe and inlet system. 
Status Details The final plans for the project are complete. Project has been advertised for bidding. Bids will be taken on 5/27/2021.

11/2/2021 UPDATE: The majority of the CMP Replacement work is completed. Lining of 3 pipes is scheduled to be completed by 11/19/2021. Utility relocations are holding up work in a few yards. Evergy has encountered rock and that is slowing their progress to a snail's pace. Evergy will update the City on 11/5/2021 regarding status with rock boring and relocations.

03/02/2022 UPDATE: Although Evergy's subcontractor is in the area doing unrelated work. The City's contractor is going to push ahead and complete punch list items. Fence installation is expected to be completed soon and sod installation is expected to start on 3/2 or 3/3.

06/08/2022 UPDATE: This project is substantially completed and final quantities are being computed. 
Contact Phone 913-742-6236
Contact Email cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3518
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson Associates
Construction Contract VF Anderson Builders
Inspection Firm Olsson Associates
Start Date 07-12-2021
Estimated End Date 03-31-2022
Budget Information
As of Jun 2 2022
Current Budget $557,800.00
Current Commitments $362,087.00
Paid-to-Date $334,696.00
Percentage Paid 92%