Name |
67th Street and Cottonwood Drive Storm Drainage Improvements |
Date Updated |
06-07-2023 |
Contact |
Ernie Longoria, P.E., PTOE |
Project Status |
Construction |
Description |
The project will include replacement of existing 10’ x 6’ RCB under 67th Street and the existing 10’ x 8’ RCB under Cottonwood Drive, replacement of a storm sewer system along 67th Street, sanitary sewer encasement/relocation, bank stabilization/wall construction along the banks of the existing channel, parking lot reconstruction at 13902 W 67th Street, and associated pavement replacement along 67"‘ Street and Cottonwood Drive. |
Status Details |
JCW revisions have been made and resubmitted. KDHE permit issued. Corps of Engineers permit with mitigation requirements provided to the City.
Project awarded at January 9th City Council. A preconstruction meeting was held on February 24th.
Contractor has completed sanitary sewer line installation and is pressure testing this week. Work will next move to completing vacating the old sanitary main and then installing the Cottonwood Drive culvert.
|
Contact Phone |
913-742-6312 |
Contact Email |
elongoria@cityofshawnee.org |
This Is a City Project |
|
Number |
3464 |
This Is a Capital Improvement Project |
|
Project Category |
Drainage Improvements |
Design Firm |
Renaissance Infrastructure Consulting |
Construction Contract |
VF Anderson Builders |
Inspection Firm |
Renaissance Infrastructure Consulting |
Start Date |
03-01-2023 |
Estimated End Date |
10-01-2023 |