67th Street and Cottonwood Drive Storm Drainage Improvements
Name 67th Street and Cottonwood Drive Storm Drainage Improvements
Date Updated 11-02-2023
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description The project will include replacement of existing 10’
x 6’ RCB under 67th Street and the existing 10’ x 8’ RCB under Cottonwood Drive,
replacement of a storm sewer system along 67th Street, sanitary sewer encasement/relocation,
bank stabilization/wall construction along the banks of the existing channel, parking
lot reconstruction at 13902 W 67th Street, and associated pavement replacement along
67"‘ Street and Cottonwood Drive.
Status Details 67th Street and Cottonwood Drive are reopened to traffic with temporary road base.  Construction is progressing with large block retaining walls south of 67th Street.  Asphalt paving is planned the week of November 6th.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3464
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Renaissance Infrastructure Consulting
Construction Contract VF Anderson Builders
Inspection Firm Renaissance Infrastructure Consulting
Start Date 03-01-2023
Estimated End Date 11-29-2023
Budget Information
As of Nov 1 2023
Current Budget $4,415,893.00
Current Commitments $4,019,636.90
Paid-to-Date $2,698,713.00
Percentage Paid 67%
Project Files
File Name
Download
21_0108 67th and Cottonwood Final Plan Submittal 2022_07_18.pdf
Project Images
File Name
View
Download
20181001_145843.jpg
20181001_144427.jpg
20181001_143939.jpg
20181001_144956.jpg
20181001_150210.jpg
20210121_150924.jpg
20210121_151554.jpg