Name |
67th Street and Cottonwood Drive Storm Drainage Improvements |
Date Updated |
11-02-2023 |
Contact |
Ernie Longoria, P.E., PTOE |
Project Status |
Construction |
Description |
The project will include replacement of existing 10’ x 6’ RCB under 67th Street and the existing 10’ x 8’ RCB under Cottonwood Drive, replacement of a storm sewer system along 67th Street, sanitary sewer encasement/relocation, bank stabilization/wall construction along the banks of the existing channel, parking lot reconstruction at 13902 W 67th Street, and associated pavement replacement along 67"‘ Street and Cottonwood Drive. |
Status Details |
67th Street and Cottonwood Drive are reopened to traffic with temporary road base. Construction is progressing with large block retaining walls south of 67th Street. Asphalt paving is planned the week of November 6th. |
Contact Phone |
913-742-6312 |
Contact Email |
elongoria@cityofshawnee.org |
This Is a City Project |
|
Number |
3464 |
This Is a Capital Improvement Project |
|
Project Category |
Drainage Improvements |
Design Firm |
Renaissance Infrastructure Consulting |
Construction Contract |
VF Anderson Builders |
Inspection Firm |
Renaissance Infrastructure Consulting |
Start Date |
03-01-2023 |
Estimated End Date |
11-29-2023 |