67th Street and Cottonwood Drive Storm Drainage Improvements
Name 67th Street and Cottonwood Drive Storm Drainage Improvements
Date Updated 04-05-2021
Contact Ernie Longoria, P.E., PTOE
Project Status Design
Description The project will include replacement of existing 10’
x 6’ RCB under 67th Street and the existing 10’ x 8’ RCB under Cottonwood Drive,
replacement of a storm sewer system along 67th Street, sanitary sewer encasement/relocation,
bank stabilization/wall construction along the banks of the existing channel, parking
lot reconstruction at 13902 W 67th Street, and associated pavement replacement along
67"‘ Street and Cottonwood Drive.
Status Details Surveying and soil borings are complete.  Preliminary Design is underway.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3464
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Renaissance Infrastructure Consulting
Construction Contract TBD
Inspection Firm Renaissance Infrastructure Consulting
Start Date 08-05-2021
Estimated End Date 01-12-2022
Budget Information
As of May 5 2021
Current Budget $3,167,180.00
Current Commitments $577,765.00
Paid-to-Date $67,137.00
Percentage Paid 11%