Goddard Reconstruction - 55th Street to Johnson Drive
Name Goddard Reconstruction - 55th Street to Johnson Drive
Date Updated 06-17-2022
Contact Cody Wilbers, P.E.
Project Status Construction
Description Reconstruction of Goddard Street, from 55th Street to Johnson Drive.  This project will include new pavement, curbs, sidewalks, storm drainage, street lighting, pavement markings, and signing.
Status Details The City worked with Walter P. Moore to complete the Engineering Design and develop plans and specifications.  The project was awarded to V.F. Anderson and construction started on May 16, 2022 with completion in early October of 2022. 

The roadway is currently closed from 56th Street to 57th Terrace and will be until mid to late July.  Utility relocations are ongoing and near completion.
Contact Phone 913-742-6234
Contact Email cwilbers@cityofshawnee.org
This Is a City Project
Number 3523
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Walter P. Moore 
Construction Contract V.F Anderson
Inspection Firm Benesch
Start Date 05-02-2022
Estimated End Date 09-19-2022
Budget Information
As of Jun 2 2022
Current Budget $2,900,000.00
Current Commitments $2,189,541.13
Paid-to-Date $330,825.00
Percentage Paid 15%
Project Files
File Name
Download
3523_Goddard_Final Plans.pdf
Goddard 08.24.21 Public Meeting.pptx
Goddard Street_Public Meeting_Audio and Visuals.mp4
Project Images
File Name
View
Download
No images to show...