43rd Street and K-7 Highway intersection street improvements
Name 43rd Street and K-7 Highway intersection street improvements
Date Updated 08-09-2021
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description Intersection improvements include additional turn lanes at intersection approaches, acceleration lanes from 43rd Street, traffic signal, traffic camera and a culvert extension improvements.
Status Details Project has been awarded.  Construction is expected to begin April 19th.  Work is expected to last 5 months.

8/9 Update:  Permanent poles and signals are in place and functioning with a temporary signal controller.  The permanent controller has been shipped and will be installed upon arrival.  Concrete base has been placed for shoulder widening and is awaiting cure time.  The week of 8/16 will see asphalt paving on shoulders and approaches as well as on Coleman Equipment's relocated entrance.  Traffic Control will then be adjusted to shift K-7 traffic to the outer lanes to complete additional left turn lanes.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3512
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm RIC
Construction Contract Linaweaver Construction
Inspection Firm RIC
Start Date 04-19-2021
Estimated End Date 09-27-2021
Budget Information
As of Sep 7 2021
Current Budget $2,645,354.00
Current Commitments $2,354,403.35
Paid-to-Date $531,870.00
Percentage Paid 22%
Project Files
File Name
Download
021621 virtual public meeting43rd Street K7 Improvements.pdf
Project Images
File Name
View
Download
43rd street looking east.png
K7 looking north.png
Project vicinity map with project limits.png