K-7 intersection improvements at 43rd Street
Name K-7 intersection improvements at 43rd Street
Date Updated 11-16-2020
Contact Ernie Longoria, P.E., PTOE
Project Status Design
Description Intersection improvements include additional turnlanes, acceleration lanes from 43rd Street and a culvert extension as well as KC SCOUT improvements.
Status Details Project is in final design with KDOT and is planned to be advertised in December.  Work is expected to last 4 months.
Contact Phone 913-742-3243
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3512
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm RIC
Construction Contract TBD
Inspection Firm RIC
Start Date 01-01-2021
Estimated End Date 04-30-2021
Budget Information
As of Jan 8 2021
Current Budget $1,761,800.00
Current Commitments $0.00
Paid-to-Date $0.00
Percentage Paid 0%