67th & Midland Stormwater CMP Replacement Project and 68th and Midland Sidewalk Infill Project
Name 67th & Midland Stormwater CMP Replacement Project and 68th and Midland Sidewalk Infill Project
Date Updated 04-26-2021
Contact Cynthia Moeller-Krass
Project Status Construction
Description A storm drainage project is scheduled to take place on Midland, from 67th Street south approximately 950'.  The project will remove and replace a 30" failing pipe located on the west side of Midland.  The 68th and Midland Sidewalk Infill Project was added to the drainage project by Governing Body authorization in January 2021.
Status Details The bid opening for this project was 10/30/20.  The City Council awarded this project to Kansas Heavy Construction, LLC, on 11/9/20, in the amount of $258,038.50.  The project is anticipated to begin December 2020, weather permitting.

4/7/2021  UPDATE - Delays in pre-construction utility relocations are delaying the project. AT&T lines need to be spliced over Kansas Heavy can begin which will likely be closer to May 1st. In addition, on 1/22/2021 the City Council authorized the addition of sidewalk extension on the west side of Midland down to 68th Ter. This work has been added to the project. Additional utility relocations are expected for this work and this too may delay this additional work.

4/26/2021 UPDATE - The contractor will be starting the main stormwater replacement this week as AT&T has completed utility relocation of the north portion the project.  AT&T still has to complete relocation work before the 68th and Midland sidewalk work can be replace.  
Contact Phone 913-742-6236
Contact Email Cmoeller-krass@cityofshawnee.org
This Is a City Project
Number 3519
This Is a Capital Improvement Project
Project Category Drainage Improvements
Design Firm Olsson Associates
Construction Contract $258,038.50
Inspection Firm Olsson Associates
Start Date 12-15-2020
Estimated End Date 06-04-2021
Budget Information
As of May 5 2021
Current Budget $598,400.00
Current Commitments $258,038.50
Paid-to-Date $0.00
Percentage Paid 0%