Status Details |
12/10/20: The Notice to Proceed has been issued for Monday, December 14, 2020. This project is a 180 day project and the anticipated project completion date is June 15, 2021 except for final sod on a few locations. Repairs completed after May 15th will not receive sod until after Labor Day.
03/01/21 UPDATE: The below noted Maps are under construction and approximately 15% of the work is in various construction phases. Substantially Complete - Maps 1, 2, 3, 6, 12, 13, 15 and Alt 8. In Progress - Maps 5, 8, 17, Alt 1 and Alt 11. 04/05/21 UPDATE: The below noted Maps are under construction and approximately 42% of the work is in various construction phases. Substantially Complete - Maps 1, 2, 3, 5, 6, 12, 13, 15 , 17, 25, Alt 1, Alt 8 and Alt 11. In Progress - Maps 8, 9, 21, 22, 23, 24, Alt 2, Alt 3, Alt 5, Alt 9, and Alt 10.
5/19/2021 UPDATE: Two additional emergency repair locations are being added to the contract. Map #26 - 56th Ter & Brockway Map #27 - Mullen & Johnson Drive
5/25/21 - 04/05/21 The below noted Maps are under construction and approximately 65% of the work is in various construction phases. Completed - Maps 1, 2, 3, 5, 6, 9, 12, 13, 15, 17, 25, Alt 2, Alt 3, Alt 8.
Substantially Complete - Maps 21, 24, Alt 1, Alt 9, Alt 10, Alt 11. In Progress - Maps 4, 8, 14, 16, 18, 22, 23, Alt 5 and Alt 7.
7/19/21 - The below noted Maps are under construction. Approximately 92% of the work is completed on this project. Completed - Maps 1, 2, 3, 4, 5, 6, 9, 12, 13, 15, 17, 21, 22, 24, 25, Alt 2, and Alt 8.
Substantially Complete - Maps Alt 9 & Alt 10. In Progress - Maps 8, 14, 15, 16, 18, 22, 23, 26, Alt 1, Alt 3, Alt 5, Alt 7 and 27.
9/28/21 - All the work on the various Maps is complete. Approximately 96% of the work is completed on this project with a few areas remaining to sod and finish.
11/02/2021 - Sod will be installed at final locations Maps 27 and Alt 7 in next 10 days. Map 8 is scheduled to be completed, weather dependent, 11/10/2021. 02/24/2022 - Contractor is working on Punch List items.
03/02/22 - Contractor is working on Punch list items and is scheduled to complete project by 03/31/2022.
|