43rd Street - Frisbee Road to K-7 Highway
Name 43rd Street - Frisbee Road to K-7 Highway
Date Updated 04-29-2021
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description Reconstruction of 43rd Street.  The improvements will provide a new drainage ditch section, concrete street, pavement markings, shared use path and luminaires.
Status Details Notice to Proceed was issued on 7/29/20.  The contractor is beginning mobilization activities.  Phase 1 activities is to be complete by 12/18/20 and Phase 2 and project close out is due by 6/24/21.

4/29/21 UPDATE:  Utility relocations are complete.  Finished shoulders and ditches are being graded.  Remaining concrete pavement is scheduled to begin the week of 5/3 starting on the east end by the K-7 intersection, weather permitting.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3498
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Renaissance Infrastructure Consulting, Inc.
Construction Contract HB Construction
Inspection Firm Renaissance Infrastructure Consulting, Inc.
Start Date 07-29-2020
Estimated End Date 06-24-2021
Budget Information
As of May 5 2021
Current Budget $5,228,465.00
Current Commitments $4,433,739.57
Paid-to-Date $2,772,460.00
Percentage Paid 62%