43rd Street - Frisbee Road to K-7 Highway
Name 43rd Street - Frisbee Road to K-7 Highway
Date Updated 08-09-2021
Contact Ernie Longoria, P.E., PTOE
Project Status Construction
Description Reconstruction of 43rd Street.  The improvements will provide a new drainage ditch section, concrete street, pavement markings, shared use path and luminaires.
Status Details Notice to Proceed was issued on 7/29/20.  The contractor is beginning mobilization activities.  Phase 1 activities is to be complete by 12/18/20 and Phase 2 and project close out is due by 6/24/21.

8/9/21 UPDATE:  Paving is complete.  Working on final stabilization, pavement markings, trail, and streetlight acceptance to complete work.  A section of 43rd will remain unpaved for an additional 3 months to allow for hauling of fill material from the south to the north side for future development.
Contact Phone 913-742-6312
Contact Email elongoria@cityofshawnee.org
This Is a City Project
Number 3498
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Renaissance Infrastructure Consulting, Inc.
Construction Contract HB Construction
Inspection Firm Renaissance Infrastructure Consulting, Inc.
Start Date 07-29-2020
Estimated End Date 08-20-2021
Budget Information
As of Sep 7 2021
Current Budget $5,228,465.00
Current Commitments $4,641,331.49
Paid-to-Date $4,466,460.00
Percentage Paid 96%