60th Street - Flint to Nieman Road
Name 60th Street - Flint to Nieman Road
Date Updated 11-03-2020
Contact Riley McMullin
Project Status Construction
Description This is a complete reconstruction project along 60th Street, between Flint and Nieman Road.  This will include grading, new pavement, curb, sidewalk, streetlights, ADA ramps, storm sewer facilities, and signing.  
Status Details The project was bid on August 5th, and approved at the August 24 City Council meeting. The contract is Amino Brothers Construction and work is expected to begin on September 8th, 2020.  There will be ongoing utility work being completed within the next few weeks.  All work is to be completed by the second week of November
Contact Phone 913-742-6224
Contact Email rmcmullin@cityofshawnee.org
This Is a City Project
Number 3505
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Walter P. Moore
Construction Contract Amino Brothers Construction
Inspection Firm BHC
Start Date 09-08-2020
Estimated End Date 11-13-2020
Budget Information
As of Jan 8 2021
Current Budget $1,200,000.00
Current Commitments $723,146.95
Paid-to-Date $441,008.00
Percentage Paid 60%
Project Files
File Name
Download
2020_05_14_Field_Check_Plan_Submittal.pdf
3505_60th_Street_Final_Plans_7_10_20.pdf
Project Images
File Name
View
Download