Flint Street - 62nd Terrace to Johnson Drive
Name Flint Street - 62nd Terrace to Johnson Drive
Date Updated 10-15-2018
Contact Paul Lindstrom, P.E.
Project Status Construction
Description This is a new project that is included as the first project within the Street Improvement Program (SIP).  This work involves complete removal and replacement of the existing street and will include grading, widening, curb, sidewalk/ADA ramps, storm drainage facilities, recreational trail on the north end, pavement markings, and LED streetlight luminaires.  The new storm drainage improvements will connect into the proposed improvements from the Nieman North drainage project.
Status Details This project is being built through the Design-Build process whereas the designer and contractor work together and provide a final product to the City for a set maximum dollar amount. The City Council has entered into a phase II contract with the design build team of Emery Sapp & Sons / Shafer Kline & Warren to provide Design-Build services for this project.

The first step for this project was to conduct a neighborhood meeting to gather public input and to discuss features to be included with the project. This neighborhood meeting was held on September 28, 2017. A second neighborhood meeting was held February 7, 2018 to share design concepts and update the public on the preliminary plans for the project. Preliminary plans were approved by the Governing Body at the February 26, 2018 City Council meeting. Final plans for the project were approved by the Governing Body at the May 14, 2018 City Council meeting. The approved final project plans are attached below.

The utility relocation work along Flint Street is almost complete with only a few utility providers still finishing their work. Currently the Design-Builder is completing driveway and sidewalk installation throughout the project. The project is scheduled to be substantially complete by November 1, 2018. 
Contact Phone (913)742-6234
Contact Email plindstrom@cityofshawnee.org
This Is a City Project
Number 3432
This Is a Capital Improvement Project
Project Category Street Improvements
Design Firm Shafer Kline & Warren
Construction Contract Emery Sapp & Sons
Inspection Firm TBD
Start Date 09-11-2018
Estimated End Date 11-02-2018
Project Notices
File Name
Download
Flint Street-Final Construction Plans-180511.pdf
Flint Street-Final Plan Development Summary & Report-180510.pdf
Project Images
File Name
View
Download
No images to show...
Silk UI Framework Simulation Device
Resize the window to preview the page in target devices.
Open the settings to change the simulation device options.
Click here to see your activities